How do I change the project calander from 5 day to 7 day week?
Dear all,
I am having a project which spans from May 06 to Jan 08. I have set up the project calendar with holidays as nonworking days and 5 day working week. However, now i want to change holiday non-work days to work days, change 7 day working week and reflect the same in completed and in-progress and scheduled activities as well.
Re: How do I change the project calander from 5 day to 7 day week?
See you can change your current working calendar to 7 day working week but i doubt if you will be able to convert company holidays to working days. On the other hand i don't think that it will make any sense if you will try to reflect it in completed and in-progress and scheduled activities. If possible open the working time calendar and from today set all all weekends and future holidays as nondefault working time. After that go in to tools/Options/Calendar tab and set Hours per week to be 56 if you are using 8 hour work day.If not, then you can set it accordingly.