I’m using Microsoft Project 2003. We have created a Gantt where when we check the Detail Gantt and Leveling Gantt views, there is a Leveling field whose units are in ‘edays’.
What is this eday? What actually it stands for? Any help please?
Printable View
I’m using Microsoft Project 2003. We have created a Gantt where when we check the Detail Gantt and Leveling Gantt views, there is a Leveling field whose units are in ‘edays’.
What is this eday? What actually it stands for? Any help please?
Eday is just a number of calendar days rather than business days. If you want you can also enter your task duration in terms of edays. This can be very helpful in case you have tasks which do not obey working hours