Analyzing EVA in MS Project 2007
My numbers:
Baseline: 1631
Actual: 1280,8
EAC: 1383,63
From the attachment:
Earned Value at completion: 1498
Planned Value at completion: 1593
Actual Cost at completion: 1229
What I don't understand is why the PV is not equal to the baseline? And why isn't the EV at completion the same as the PV at completion? All my tasks are set to 100% complete.
Is it just me, or are these numbers kinda strange?
Re: Analyzing EVA in MS Project 2007
Re: Analyzing EVA in MS Project 2007
To calculate EVA in MS project just visit the following link, where you get the satisfactory answer to your question.
http://www.gantthead.com/article.cfm?ID=225763
Thanks amgravem