Go Back   TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Become a Member!
Forgot your username/password?
Register Tags Active Topics RSS Search Mark Forums Read SiteMap

Tags: , ,

Sponsored Links



How do I change the project calander from 5 day to 7 day week?

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 02-05-2008
Gary48
 
Posts: n/a
How do I change the project calander from 5 day to 7 day week?

I have a project that spans from May 06 to Jan 08. The project calander was
initially set up with holidays as non work days and a 5 day work week. I
want to change holiday non-work days to work days and change to a 7 day work
week and reflect this in completed as well as in-progress and scheduled
activities.
Reply With Quote
  #2  
Old 02-05-2008
John
 
Posts: n/a
Re: How do I change the project calander from 5 day to 7 day week?

In article <E8B08599-BEBB-43C9-A394-B2448A8828AD@microsoft.com>,
Gary48 <Gary48@discussions.microsoft.com> wrote:

> I have a project that spans from May 06 to Jan 08. The project calander was
> initially set up with holidays as non work days and a 5 day work week. I
> want to change holiday non-work days to work days and change to a 7 day work
> week and reflect this in completed as well as in-progress and scheduled
> activities.


Gary48,
You can change the working calendar to have a seven day work week but I
question the validity of converting company holidays to work days and
the idea of trying to do this for completed tasks makes no sense at all
- history is history - it's done.

I suggest you open the working time calendar (Tools/Change Working Time)
and starting from today, make all weekends and future holidays (if you
really must) nondefault working time. Then go to Tools/Options/Calendar
tab and set the Hours per week to be 56, assuming you are still using a
standard 8 hour work day. I wouldn't change the Days per month because
it can never truly reflect a seven day work week.

John
Project MVP
Reply With Quote
  #3  
Old 02-05-2008
Member
 
Join Date: Apr 2008
Posts: 1
Hello Gary,

if you go to tools, change working time. You can set the new calander by goint to exceptions, deleting the holiday exceptions leaving you with just the working time exception. Click on details where you can set your daily working hours by selecting working times and entering your hours, then select weekly and highlight all seven days. Then by setting the range of recurrence to be from the start date to end date of your project it should change the working times of past progress. However, whichever way you have been updating you progress until now will mean that certain start dates entered or % complete per week for example means that your progress wont be fully spread to fill your new working hours.

hope this is of help

frank
Reply With Quote
  #4  
Old 02-05-2008
Gary48
 
Posts: n/a
Re: How do I change the project calander from 5 day to 7 day week?

Thanks John...and you're right about completed tasks. This helps.

Gary

"John" wrote:

> In article <E8B08599-BEBB-43C9-A394-B2448A8828AD@microsoft.com>,
> Gary48 <Gary48@discussions.microsoft.com> wrote:
>
> > I have a project that spans from May 06 to Jan 08. The project calander was
> > initially set up with holidays as non work days and a 5 day work week. I
> > want to change holiday non-work days to work days and change to a 7 day work
> > week and reflect this in completed as well as in-progress and scheduled
> > activities.

>
> Gary48,
> You can change the working calendar to have a seven day work week but I
> question the validity of converting company holidays to work days and
> the idea of trying to do this for completed tasks makes no sense at all
> - history is history - it's done.
>
> I suggest you open the working time calendar (Tools/Change Working Time)
> and starting from today, make all weekends and future holidays (if you
> really must) nondefault working time. Then go to Tools/Options/Calendar
> tab and set the Hours per week to be 56, assuming you are still using a
> standard 8 hour work day. I wouldn't change the Days per month because
> it can never truly reflect a seven day work week.
>
> John
> Project MVP
>

Reply With Quote
  #5  
Old 02-05-2008
John
 
Posts: n/a
Re: How do I change the project calander from 5 day to 7 day week?

In article <237B7124-945F-4AF7-9A6A-0C533D583044@microsoft.com>,
Gary48 <Gary48@discussions.microsoft.com> wrote:

> Thanks John...and you're right about completed tasks. This helps.
>
> Gary


Gary,
You're welcome and thanks for the feedback.
John
>
> "John" wrote:
>
> > In article <E8B08599-BEBB-43C9-A394-B2448A8828AD@microsoft.com>,
> > Gary48 <Gary48@discussions.microsoft.com> wrote:
> >
> > > I have a project that spans from May 06 to Jan 08. The project calander
> > > was
> > > initially set up with holidays as non work days and a 5 day work week. I
> > > want to change holiday non-work days to work days and change to a 7 day
> > > work
> > > week and reflect this in completed as well as in-progress and scheduled
> > > activities.

> >
> > Gary48,
> > You can change the working calendar to have a seven day work week but I
> > question the validity of converting company holidays to work days and
> > the idea of trying to do this for completed tasks makes no sense at all
> > - history is history - it's done.
> >
> > I suggest you open the working time calendar (Tools/Change Working Time)
> > and starting from today, make all weekends and future holidays (if you
> > really must) nondefault working time. Then go to Tools/Options/Calendar
> > tab and set the Hours per week to be 56, assuming you are still using a
> > standard 8 hour work day. I wouldn't change the Days per month because
> > it can never truly reflect a seven day work week.
> >
> > John
> > Project MVP
> >

Reply With Quote
  #6  
Old 05-05-2008
Steve House
 
Posts: n/a
Re: How do I change the project calander from 5 day to 7 day week?

Do you mean your resources will never get a day off between May and
January????? That's what setting a 7 day work-week implies - not just that
we have various work schedules that overlap to cover all 7 days of the week
but rather no one on the project team ever gets a day off between when the
project starts and when it ends. If all your resources are machines -
maybe - but human beings can't work that way.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Gary48" <Gary48@discussions.microsoft.com> wrote in message
news:E8B08599-BEBB-43C9-A394-B2448A8828AD@microsoft.com...
>I have a project that spans from May 06 to Jan 08. The project calander
>was
> initially set up with holidays as non work days and a 5 day work week. I
> want to change holiday non-work days to work days and change to a 7 day
> work
> week and reflect this in completed as well as in-progress and scheduled
> activities.


Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "How do I change the project calander from 5 day to 7 day week?"
Thread Thread Starter Forum Replies Last Post
MS Project Scheduling on specific day of week jwiesner Windows Software 1 2 Weeks Ago 01:22 AM
MS project: change the week end in the calendar Mohammed-aqel Windows Software 1 04-10-2011 01:15 AM
Vodafone Super Week: Free access to Facebook, Orkut and Twitter for a week! Fulton1990 India BroadBand 5 11-05-2011 04:01 PM
MS project - cannot change working day msprojectuser50 Windows Software 1 10-11-2010 04:26 PM
Change Hours in a Work Week Steve Microsoft Project 13 29-10-2008 10:59 PM


All times are GMT +5.5. The time now is 05:37 PM.