|
| |||||||||
| Tags: calculation, duration, incorrect |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| incorrect duration calculation....
I am using the Gantt view of Microsoft Project. I have entered correct start and end dates for my task (I have not created subtasks yet). The duration that Microsoft project is populating is horribly wrong! For example I have a start date 16/10/06 of and an end date of 20/11/06 and it is suggesting a duration of 106.13 days. I can't see where these two decimal points are coming from and how I can correct this. I have attempted to toy with the calendar/schedule and work time settings. But no joy! Any help would be greatly appreciated! Thanks, Em |
|
#2
| |||
| |||
| RE: incorrect duration calculation....
Hi Emily, You should not be entering dates into MS Project as this creates constraints. The dates in Project are calculated based upon the start date of the project, the project calendar, the definition of hours per day and hours per week, and predecessor/successor relationships. You may want to take some time and read through Mike Glen's excellent series of articles on using MS Project at: http://project.mvps.org/mike's_tutorials.htm I hope this helps. Let us know how you get along. Julie "EmilyO" wrote: > I am using the Gantt view of Microsoft Project. I have entered correct start > and end dates for my task (I have not created subtasks yet). The duration > that Microsoft project is populating is horribly wrong! > > For example I have a start date 16/10/06 of and an end date of 20/11/06 and > it is suggesting a duration of 106.13 days. > > I can't see where these two decimal points are coming from and how I can > correct this. I have attempted to toy with the calendar/schedule and work > time settings. But no joy! > > Any help would be greatly appreciated! > > Thanks, > Em |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "incorrect duration calculation...." | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Incorrect end date for a task with the same duration | vsaddepalli | Microsoft Project | 2 | 14-12-2011 10:15 PM |
| incorrect duration calculation | J_R12 | Microsoft Project | 2 | 16-10-2011 09:07 PM |
| Task Duration Varies as Project Duration Varies ... ? | CeeTee | Microsoft Project | 4 | 16-01-2009 05:52 PM |
| Summary Task Duration incorrect | redmadcap | Microsoft Project | 4 | 10-10-2008 08:37 AM |
| duration calculation doesn't skip non-working days | Scott | Microsoft Project | 4 | 24-01-2008 05:12 AM |