    Resource Usage View

    I am administering a Resource Pool in Project 2010. In the resource useage view I see all my resources and underneath each the tasks that they are assigned to. Ive been asked to produce a view that shows each task and underneath each the resource names assigned to the task. Anyone know if this is possible and if so how?

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    re: Resource Usage View

    Have you looked at the Task Usage view in the master project? Open the Resource Pool file and select the 3rd option. That will create a master project and if you look at the Task Usage view you should see what you are seeking -- each task and underneath each task the assignment information - represented by the name of the resource.

    I hope this helps.

    Julie

  3. #3
    Join Date
    Jul 2009
    Posts
    67

    Re: Resource Usage View

    Thanks for your advice JulieS. However when I look at the resource useage view in my 'Project' (not the resource pool its linked to) all I see is each resouce and underneath the the tasks they are assigned to. Same as before.

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: Resource Usage View

    Re-read my post -- I suggested you use the Task Usage view in a consolidate project.

    Julie

  5. #5
    Join Date
    Jul 2009
    Posts
    67

    Re: Resource Usage View

    My mistake - I should be looking at the Task useage view NOT the Resource useage view shouldnt I ?! I see what I want now thanks for your help.

  6. #6
    Join Date
    Dec 2006
    Posts
    489

    Re: Resource Usage View

    Great. Glad the Task Usage view gives you what you need.

    Julie

Similar Threads

  1. Replies: 6
    Last Post: 24-09-2011, 01:32 AM
  2. Summarize Task on Resource Usage View/Reports
    By Deabelos in forum Microsoft Project
    Replies: 3
    Last Post: 08-01-2011, 06:07 AM
  3. Resource usage view
    By CBnation in forum Microsoft Project
    Replies: 2
    Last Post: 07-10-2010, 04:24 PM
  4. Resource Usage Display (Just Months)
    By richme in forum Windows Software
    Replies: 1
    Last Post: 01-05-2010, 05:22 PM
  5. Replies: 2
    Last Post: 09-09-2009, 09:40 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,310,667.20730 seconds with 17 queries