| Actual cost between specific dates
I want to insert a Column in Gantt Chat that returns the actual cost between two specific dates (for example, to return the actual cost only in march 2012). I already tried macros and formulating in costum fields, but i didnt achieve what i want. |
|
#2
| ||||
| ||||
| Re: Actual cost between specific dates
If you look at the Task Usage view, add costs to the right side and zoom out to show months, this should show Actual Cost per month. I'm afraid there is no method of showing that information in a non-timescaled view such as a column in the Gantt chart view. |
|
#3
| |||
| |||
| Re: Actual cost between specific dates
Thanks for you help. That is a good alternative for what i need. |
|
#4
| ||||
| ||||
| Re: Actual cost between specific dates
You're welcome and thanks for the feedback. |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Actual cost between specific dates" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Need Suggestion for Repairing cost and Replacement cost for BIOS | Kaesini | Motherboard Processor & RAM | 8 | 04-02-2012 11:11 AM |
| Visual Report - Budget cost report without baseline cost | clauz | Microsoft Project | 4 | 04-02-2012 01:09 AM |
| What can be the actual cost of Sprint SERO 500 plan | O'Shea | Portable Devices | 9 | 18-01-2012 10:57 PM |
| Cash Flow Report Total Cost Does Not Match Gantt Total Cost? | kaorisdad | Microsoft Project | 5 | 26-08-2011 06:50 AM |
| MS Project 2007 Task Usage - Baseline Cost / Work vs. Current Cost / Work | Planning_Nate | Microsoft Project | 3 | 29-06-2011 09:31 PM |