Thread: Project 2007 tasks skipping days

  1. #1
    Join Date
    Mar 2012
    Posts
    2

    Project 2007 tasks skipping days

    I have a project where all tasks are 1 day durations (very small project, so I'm not worried about exact effort). When I schedule tasks with dependencies, the tasks end up skipping days.

    For example, task 2 starts on Wednesday 4/4, ends on Wednesday 4/4 with a duration of 1 day (task 1 is a milestone). When I setup task 3 with a predecessor of 2FS+1d, it schedules it for Friday 4/6/12, skipping Thursday. I even looked at the resource usage table and Thursday has nothing associated with it. This pattern repeats for the rest of the tasks in this project.

    Any ideas on what I can do to fix this? I've never had Project do this to me before.

  2. #2
    Join Date
    Aug 2006
    Posts
    201

    Re: Project 2007 tasks skipping days

    It is just because there is a one-day lag time (Thursday) between Task 2 and Task 3. Here are some articles on it:
    http://office.microsoft.com/en-us/pr...045295228.aspx
    http://office.microsoft.com/en-us/pr...010156787.aspx

  3. #3
    Join Date
    Mar 2012
    Posts
    2

    Re: Project 2007 tasks skipping days

    DOH! Ok, now I feel like an idiot :). Thanks alot!!
    Seriously though, thanks for the quick response.

  4. #4
    Join Date
    Aug 2006
    Posts
    201

    Re: Project 2007 tasks skipping days

    You're welcome and thanks for the feedback.

Similar Threads

  1. Updating tasks in Project 03
    By Elissajane123 in forum Windows Software
    Replies: 1
    Last Post: 15-09-2011, 10:55 AM
  2. project with tasks and sub tasks
    By 54234121 in forum Windows Software
    Replies: 2
    Last Post: 29-04-2011, 11:47 AM
  3. Project: resource use on tasks
    By proj03 in forum Windows Software
    Replies: 1
    Last Post: 28-01-2011, 11:12 AM
  4. MS Project 2007 - Help with Durations/Tasks
    By zel0 in forum Windows Software
    Replies: 1
    Last Post: 28-01-2010, 06:47 AM
  5. MS Project - Updating tasks
    By shoppingboy in forum Windows Software
    Replies: 4
    Last Post: 14-12-2009, 04:40 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,647,143.39260 seconds with 17 queries