| Project 2007 tasks skipping days
For example, task 2 starts on Wednesday 4/4, ends on Wednesday 4/4 with a duration of 1 day (task 1 is a milestone). When I setup task 3 with a predecessor of 2FS+1d, it schedules it for Friday 4/6/12, skipping Thursday. I even looked at the resource usage table and Thursday has nothing associated with it. This pattern repeats for the rest of the tasks in this project. Any ideas on what I can do to fix this? I've never had Project do this to me before. |
|
#2
| ||||
| ||||
| Re: Project 2007 tasks skipping days
It is just because there is a one-day lag time (Thursday) between Task 2 and Task 3. Here are some articles on it: http://office.microsoft.com/en-us/pr...045295228.aspx http://office.microsoft.com/en-us/pr...010156787.aspx |
|
#3
| |||
| |||
| Re: Project 2007 tasks skipping days
DOH! Ok, now I feel like an idiot :). Thanks alot!! Seriously though, thanks for the quick response. |
|
#4
| ||||
| ||||
| Re: Project 2007 tasks skipping days
You're welcome and thanks for the feedback. |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Project 2007 tasks skipping days" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Linking Tasks in MS Project | Ian Thompson | Microsoft Project | 2 | 17-02-2012 08:57 PM |
| Updating tasks in Project 03 | Elissajane123 | Windows Software | 1 | 15-09-2011 10:55 AM |
| project with tasks and sub tasks | 54234121 | Windows Software | 2 | 29-04-2011 11:47 AM |
| MS Project 2007 - Help with Durations/Tasks | zel0 | Windows Software | 1 | 28-01-2010 05:47 AM |
| MS Project - Updating tasks | shoppingboy | Windows Software | 4 | 14-12-2009 03:40 PM |