Project 2007 tasks skipping days

I have a project where all tasks are 1 day durations (very small project, so I'm not worried about exact effort). When I schedule tasks with dependencies, the tasks end up skipping days.

For example, task 2 starts on Wednesday 4/4, ends on Wednesday 4/4 with a duration of 1 day (task 1 is a milestone). When I setup task 3 with a predecessor of 2FS+1d, it schedules it for Friday 4/6/12, skipping Thursday. I even looked at the resource usage table and Thursday has nothing associated with it. This pattern repeats for the rest of the tasks in this project.

Any ideas on what I can do to fix this? I've never had Project do this to me before.

Reply With Quote
  #2  
Old 29-03-2012
Member
 
Join Date: Aug 2006
Posts: 201
Re: Project 2007 tasks skipping days

It is just because there is a one-day lag time (Thursday) between Task 2 and Task 3. Here are some articles on it:
http://office.microsoft.com/en-us/pr...045295228.aspx
http://office.microsoft.com/en-us/pr...010156787.aspx
Reply With Quote
  #3  
Old 29-03-2012
Member
 
Join Date: Mar 2012
Posts: 2
Re: Project 2007 tasks skipping days

DOH! Ok, now I feel like an idiot :). Thanks alot!!
Seriously though, thanks for the quick response.
Reply With Quote
  #4  
Old 29-03-2012
Member
 
Join Date: Aug 2006
Posts: 201
Re: Project 2007 tasks skipping days

You're welcome and thanks for the feedback.
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags:



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Project 2007 tasks skipping days"
Thread Thread Starter Forum Replies Last Post
Updating tasks in Project 03 Elissajane123 Windows Software 1 15-09-2011 10:55 AM
project with tasks and sub tasks 54234121 Windows Software 2 29-04-2011 11:47 AM
Project: resource use on tasks proj03 Windows Software 1 28-01-2011 10:12 AM
MS Project 2007 - Help with Durations/Tasks zel0 Windows Software 1 28-01-2010 05:47 AM
MS Project - Updating tasks shoppingboy Windows Software 4 14-12-2009 03:40 PM


All times are GMT +5.5. The time now is 03:16 AM.