Thread: Trouble with simplying a fixed cost/fixed duration project plan

  1. #1
    Join Date
    Feb 2012
    Posts
    4

    Trouble with simplying a fixed cost/fixed duration project plan

    I have enviable task of redesigning the Company's project plan for the projects we are appointed for.

    Now, it may be a case that I am trying to be too clever with this project and will need to be happy with what I have got, but I would be grateful for comments/confirmation prior to moving on. I am using Project 2003.

    I work for a Trustee Company of pension schemes, that involve assisting Employers to wind-up pension schemes and secure members with their retirement benefits. The nature of this work means that we are ultimately responsible for each task within the project, but other third parties will be involved in completing the task. All tasks will involve a fixed cost for the Trustees work in each task, but the timescale will include the time taken for other parties to respond or simply the window of time within which the Trustees have to carry out the work. To provide an example:

    Write out to Scheme Membership: Duration – 30 days, Work - 3 hours

    The Trustees role of drafting, amending and sending the letter is equivalent to 3 hours work. The duration accounts for time it will take for 3rd parties to comment, amend and approve the letter before sending. The task is not effort driven, regardless of whether the task only takes 25 days, the work would remain at 3 hours. Likewise, if the work on the task only takes 2 hours, the duration would remain at 30 days.

    The complexity of a Pension Scheme wind-up project means there are approximately 100 tasks similar to the above, all of which account for 3rd party timescales.

    My current approach (following failed attempts to merge the above requirements) has been to divide each task, so each task has both a task in respect of the work/cost, as well as a corresponding task in respect of the duration of the task. An example:

    Write Out to Scheme Membership – Duration – 1 day, Work – 3 hours
    CL – Write Out to Scheme Membership – Duration – 29 day, Work - 0 hours

    Whilst the “splitting” approach, has allowed the project plan to flow correctly, I would prefer to eliminate this “splitting” and make the project plan more user friendly.

    Any suggestions/confirmation that my desired action is not possible would be greatly appreciated.

  2. #2
    Join Date
    Nov 2005
    Posts
    1,187

    Re: Trouble with simplying a fixed cost/fixed duration project plan

    I think I understand what you are searching for and I can propose an answer but I will also suggest that the task that you describe likely should be two tasks. There is a component that the Trustees are responsible for -- creating the initial letter. That may take a day -- and be 3 hours of work. There is then a 29 day task that is in essence, out of your direct control.

    That being said, you can accomplish what you seek - create the 30 day task and change the task type to Fixed Duration. Then assign the appropriate resource and enter the 3 hours of work. Project will spread the 3 hours work evenly across the 30 days duration. If necessary, edit the task in the Task Usage view to enter the 3 hours on the first day. Then edit the assignment line finish date to be the end of the first day. This will leave the duration to 30 days, the work to 3 hours and you will see a split (dotted lines) after the first day.

    You can certainly leave the 3 hours of work spread out across the entire 30 days.

  3. #3
    Join Date
    Feb 2012
    Posts
    4

    Re: Trouble with simplying a fixed cost/fixed duration project plan

    Thanks, I will have a go at the alternative set-up and see how I get on. Much appreciated for getting back to me so quickly.

  4. #4
    Join Date
    Nov 2005
    Posts
    1,187

    Re: Trouble with simplying a fixed cost/fixed duration project plan

    You're welcome. Feel free to post back with further questions as needed.

Similar Threads

  1. Difference between fixed work, duration and units
    By Amitgujaran in forum Microsoft Project
    Replies: 5
    Last Post: 17-12-2011, 09:37 PM
  2. Steam updating trouble fixed
    By Sitia in forum Video Games
    Replies: 8
    Last Post: 18-09-2011, 10:47 PM
  3. MS Project Fixed Duration vs Working Times
    By datadrvn in forum Microsoft Project
    Replies: 2
    Last Post: 23-06-2011, 07:20 PM
  4. GTA IV fixed
    By drumzr in forum Video Games
    Replies: 1
    Last Post: 10-12-2008, 03:17 PM
  5. Fixed Cost
    By K-Mind in forum Microsoft Project
    Replies: 2
    Last Post: 02-12-2008, 05:51 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,665,557.19459 seconds with 17 queries