    Linking a task to 2 predecessors

    I am trying to link one task to two predecessors but it msp is not taking it. I thought i used to put in the two numbers separated by a comma but this doesnt work. Any thoughts?

  2. #2
    Join Date
    Jan 2012
    Posts
    2

    Re: Linking a task to 2 predecessors

    Sorry, just figured it out. Its a semi-colon. DUH. ;;;;;

  3. #3
    Join Date
    Dec 2007
    Posts
    2,291

    Re: Linking a task to 2 predecessors

    Yes, all you have to do to link a task to 2 predecessors is:

    • Select both tasks.
    • Click the Link Tasks button on the Standard toolbar.

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: Linking a task to 2 predecessors

    Sorry, just figured it out. Its a semi-colon. DUH. ;;;;;
    Thanks for posting the resolution. For others reading the separator is driven by the regional settings on the computer.

Similar Threads

  1. Replies: 3
    Last Post: 17-01-2014, 10:37 AM
  2. Tasks Not recognizing predecessors
    By slepage in forum Microsoft Project
    Replies: 2
    Last Post: 28-11-2011, 09:36 PM
  3. Replies: 5
    Last Post: 29-09-2011, 01:03 PM
  4. MS Project 2007 not showing 3 predecessors
    By rogerkho in forum Windows Software
    Replies: 2
    Last Post: 11-02-2010, 03:02 AM
  5. How to setup Predecessors?
    By dallr in forum Microsoft Project
    Replies: 9
    Last Post: 02-03-2009, 05:41 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,622,716.26644 seconds with 16 queries