I am trying to link one task to two predecessors but it msp is not taking it. I thought i used to put in the two numbers separated by a comma but this doesnt work. Any thoughts?
I am trying to link one task to two predecessors but it msp is not taking it. I thought i used to put in the two numbers separated by a comma but this doesnt work. Any thoughts?
Sorry, just figured it out. Its a semi-colon. DUH. ;;;;;
Yes, all you have to do to link a task to 2 predecessors is:
- Select both tasks.
- Click the Link Tasks button on the Standard toolbar.
Thanks for posting the resolution. For others reading the separator is driven by the regional settings on the computer.Sorry, just figured it out. Its a semi-colon. DUH. ;;;;;