Changing task duration in the middle of project

Hi,

I am constantly having troubles with the following issue:

I use projects to plan tasks and estimate duration for tasks for the use of building machines in our factory.

I start the project off by working towards my finish date as our customers expect the product by a due date.

I then set my baseline.

I'm having problems when I run overdue, the finish date won't update.
When I run overdue, I try to change the duration of the said task that is taking more time than planned.

And I get an error because of the predecessors.

I want to find a way so that if a task is scheduled to take 3 days but due to problems it ends up taking 5 days, I want all future tasks that are linked to this and the finish date to be pushed forward by these extra 2 days.

I can send you a copy of an example projects file I already have if need be.

Can anyone help me?

Regards,


Chris

Reply With Quote
  #2  
Old 30-12-2011
Member
 
Join Date: Dec 2006
Posts: 489
Re: Changing task duration in the middle of project

Hi Chris,

If you are using Predecessors and Successors without any constraints, the dates should move. I would also suggest updating the Remaining Duration (not just duration) on in-progress tasks.

Check the following:

1. No constraints on tasks other than ASAP
2. Calculation is automatic
3. No Actual start on successor tasks that have not really been started. If the tasks have been started, then an Actual Start will not update. Check that "Split in Progress Tasks" is enable (File> Options, Schedule).

If you'd like, zip and post a copy of the file here and I'll take a look.

Julie
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: , ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Changing task duration in the middle of project"
Thread Thread Starter Forum Replies Last Post
How to view the link between the deliverable project task and the dependency project task in project pro 2010 Hevel Microsoft Project 4 20-04-2012 11:22 PM
MS Project 2007 - Parent Task Calculates Duration Incorrectly freakp Windows Software 3 28-02-2012 07:47 PM
Project 2007 summary task duration help please? KNLee Windows Software 3 24-04-2011 02:03 AM
Task duration - start set by SF, finish set by FF. Can it be done & how ? ProjNoob Windows Software 3 12-08-2009 07:11 PM
Project Professional 2007 task duration iShree Microsoft Project 3 04-08-2009 06:24 PM