    How to get the Actual% complete vs Planned % complete in MS Projects?

    Hi,

    I had a couple of queries,
    1. How can I get the comparison between Actual% Completion against Planned or Scheduled % completion (what should have been) in MS Projects 2007?
    For Example:
    I have a task with duration of 10 days, at the end of the 5th day the progress should have been 50% but the actual reported progress is 40%. Status column shows the activity as "late". Is there any column where I can also get how much should have been the progress (i.e. 50% in this case)?
    2. When we update the actual start date in the project tracking view, the Start date changes automatically. Can this be avoided?

    Thanks,
    JMN

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: How to get the Actual% complete vs Planned % complete in MS Projects?

    1. Use earned value analysis to show the difference between the Budgeted Cost of Work Scheduled (BCWS) and Actual Cost of Work Performed (ACWP) in dollars. You can also view Schedule Variance and have calculated for you a Schedule Performance Index (SP1). Do a search for Earned Value Analysis in Project 2007 volumes of information.
    2. You should save a baseline [B]before/B] tracking any progress -- a baseline is also required for earned value analysis. The baseline start date is not updated and calculated for you is the difference between baseline start and actual start.

    I hope this helps.

    Julie

Similar Threads

  1. Planned % Complete - Enterprise Field in Project Server
    By Stelladee in forum Microsoft Project
    Replies: 4
    Last Post: 14-05-2012, 07:42 PM
  2. difference between % complete and % work complete
    By sandsand24 in forum Microsoft Project
    Replies: 1
    Last Post: 02-08-2011, 04:01 PM
  3. Planned vs Actual Work and % complete
    By bigboy in forum Microsoft Project
    Replies: 3
    Last Post: 09-07-2009, 06:28 AM
  4. Planned vs. Actual
    By Pine Le in forum Microsoft Project
    Replies: 2
    Last Post: 11-04-2009, 01:22 AM
  5. Capture Actual work when a task is complete
    By DWall in forum Microsoft Project
    Replies: 2
    Last Post: 18-07-2008, 06:38 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,710,833,391.92408 seconds with 16 queries