Hi,
I had a couple of queries,
1. How can I get the comparison between Actual% Completion against Planned or Scheduled % completion (what should have been) in MS Projects 2007?
For Example:
I have a task with duration of 10 days, at the end of the 5th day the progress should have been 50% but the actual reported progress is 40%. Status column shows the activity as "late". Is there any column where I can also get how much should have been the progress (i.e. 50% in this case)?
2. When we update the actual start date in the project tracking view, the Start date changes automatically. Can this be avoided?
Thanks,
JMN