I am having two issues. 1) The end date is establish in the Project Information does not translate into resetting the dates upon my tasks. (I have all of the tasks linked with predecessors). I would like to be able to establish an end date for the project and it work backwords changing the dates on all of the tasks. 2) How do I establish 30 days between Meeting Dates with linked tasks to those meetings? (However, I don't want resources working the entire 30 days between the meetings).