Results 1 to 3 of 3

Thread: importing dates from ms excel into ms project

  1. #1
    Join Date
    Dec 2011
    Posts
    1

    importing dates from ms excel into ms project

    we have an issue where we get an excel report ( our PMO dept uses MS EXCEL) from which we have like products

    like so

    product 1 start date end date

    product 2

    .

    .

    .

    product x



    each product has a product life cycle which we are trying to put into MS project. I wanted to know a couple of things:

    -note: the products and dates change and as such need to be reflected in MS project (that is why i needed to do manual linking)



    1. is there an automatic/easier way to "link" all the start/end dates into ms project which at the moment is very cumbersome given the crazy amount of products we have (horribly manual error prone process)? via programming or maybe i can put the ms excel file into another file format which ms project can easily get somehow?



    2. I am trying to have multiple products within one project plan. So, i defined the first product and its tasks/milestones with proper linking (both kinds linking with ms excel dates and linking internally of tasks like FS/FF etc). Now is it possible to just simply copy and paste the rest without losing any linking? apparently this is also a problem i am having.



    I need serious help on this. I would really appreciate it since i am very new to ms project and trying to convince our company to use this instead of just all sorts of ms excel sheets.



    thanks

  2. #2
    Join Date
    Dec 2007
    Posts
    2,291

    Re: importing dates from ms excel into ms project

    Follow the below method and see if it works for you or not:
    1. Click Open.
    2. In the Files of type box, click the file type you want to import data from.
      • To import data from a SQL Server or Oracle Server format, click ODBC to connect to your data source, and then continue with step 5.
    3. In the Look in box, locate the folder that contains the file you want to import, and then select the file in the file list.
      • If needed, you can search for the file.
    4. Click Open.
    5. Follow the instructions in the Import Wizard to import the data you want into the proper Microsoft Office Project fields.

  3. #3
    Join Date
    Dec 2006
    Posts
    489

    Re: importing dates from ms excel into ms project

    Quote Originally Posted by tazor View Post
    we have an issue where we get an excel report ( our PMO dept uses MS EXCEL) from which we have like products

    like so

    product 1 start date end date

    product 2

    .

    .

    .

    product x



    each product has a product life cycle which we are trying to put into MS project. I wanted to know a couple of things:

    -note: the products and dates change and as such need to be reflected in MS project (that is why i needed to do manual linking)



    1. is there an automatic/easier way to "link" all the start/end dates into ms project which at the moment is very cumbersome given the crazy amount of products we have (horribly manual error prone process)? via programming or maybe i can put the ms excel file into another file format which ms project can easily get somehow?



    2. I am trying to have multiple products within one project plan. So, i defined the first product and its tasks/milestones with proper linking (both kinds linking with ms excel dates and linking internally of tasks like FS/FF etc). Now is it possible to just simply copy and paste the rest without losing any linking? apparently this is also a problem i am having.



    I need serious help on this. I would really appreciate it since i am very new to ms project and trying to convince our company to use this instead of just all sorts of ms excel sheets.



    thanks
    You can select multiple tasks and use the "Link tasks" button to link F to S sequentially. For example: Task A, Task B, Task C, Task D.
    Select all four tasks and the resulting links will be
    Task A is predecessor to Task B in a Finish to Start link
    Task B is predecessor to Task C in a Finish to Start link
    Task C is predecessor to Task D in a Finish to Start link

    To your question about copy/paste - yes. Just ensure you select by the row number to capture all task information.

    You can define predecessors in Excel and then import -- but be cautious about Task ID versus Excel row number.

    I hope this helps.
    Julie

Similar Threads

  1. MS-Project > Linked tasks, but dates dont' move
    By BefuddledSearcher in forum Windows Software
    Replies: 2
    Last Post: 30-01-2012, 08:27 PM
  2. MS Project 2003 - show dates in the header of the report
    By shoppingboy in forum Windows Software
    Replies: 2
    Last Post: 28-03-2011, 01:08 PM
  3. Subtracting dates in Project 2007
    By taylok11 in forum Windows Software
    Replies: 1
    Last Post: 25-06-2010, 12:46 PM
  4. Error on importing project in MS-Project 2003
    By fredpaquet in forum Windows Software
    Replies: 4
    Last Post: 24-04-2009, 05:06 AM
  5. Understanding Project tasks and dates
    By Javan in forum Windows Software
    Replies: 2
    Last Post: 05-09-2008, 11:32 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,473,982.07937 seconds with 17 queries