    How to link both start and finish dates to different tasks

    Is it possible to have the start date of a task be based on a predessor AND have the finish date be based on a different task. I want MS Project to calc the duration based on 2 different tasks.

  2. #2
    Join Date
    Dec 2007
    Posts
    2,291

    Re: How to link both start and finish dates to different tasks

    To link the new task, click the task that you want the new task to precede, and then click New Task on the Insert menu. If this doesn't work, on the Tools menu, click Options, and then click the Schedule tab. Make sure that the Autolink inserted or moved tasks check box is selected. To add the new task without linking it, click the task with which the new task will occur concurrently, and then drag to create the new task in a blank portion of the Network Diagram.

  3. #3
    Join Date
    Dec 2006
    Posts
    489

    Re: How to link both start and finish dates to different tasks

    Quote Originally Posted by terrymarkham View Post
    Is it possible to have the start date of a task be based on a predessor AND have the finish date be based on a different task. I want MS Project to calc the duration based on 2 different tasks.
    Hi Terry,

    It sounds like a Hammock Task would suit your needs.

    See:

    http://support.microsoft.com/kb/141733

    I hope this helps.
    Julie

  4. #4
    Join Date
    Dec 2011
    Posts
    3

    Re: How to link both start and finish dates to different tasks

    Yep...that worked great. Thanks alot for the info.

  5. #5
    Join Date
    Dec 2006
    Posts
    489

    Re: How to link both start and finish dates to different tasks

    You're welcome and thanks for the feedback.

Similar Threads

  1. MS-Project > Linked tasks, but dates dont' move
    By BefuddledSearcher in forum Windows Software
    Replies: 2
    Last Post: 30-01-2012, 08:27 PM
  2. Changing Start & Finish Dates
    By akbar in forum Microsoft Project
    Replies: 3
    Last Post: 14-04-2010, 11:33 PM
  3. Task Start & Finish dates
    By Antonio00 in forum Microsoft Project
    Replies: 6
    Last Post: 17-03-2009, 09:48 PM
  4. Finish to Finish tasks
    By GoldStein in forum Microsoft Project
    Replies: 2
    Last Post: 30-01-2009, 10:22 PM
  5. Understanding Project tasks and dates
    By Javan in forum Windows Software
    Replies: 2
    Last Post: 05-09-2008, 11:32 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,663,438.10414 seconds with 17 queries