How to link both start and finish dates to different tasks

Is it possible to have the start date of a task be based on a predessor AND have the finish date be based on a different task. I want MS Project to calc the duration based on 2 different tasks.

Reply With Quote
  #2  
Old 01-12-2011
Member
 
Join Date: Dec 2007
Posts: 2,260
Re: How to link both start and finish dates to different tasks

To link the new task, click the task that you want the new task to precede, and then click New Task on the Insert menu. If this doesn't work, on the Tools menu, click Options, and then click the Schedule tab. Make sure that the Autolink inserted or moved tasks check box is selected. To add the new task without linking it, click the task with which the new task will occur concurrently, and then drag to create the new task in a blank portion of the Network Diagram.
Reply With Quote
  #3  
Old 02-12-2011
Member
 
Join Date: Dec 2006
Posts: 489
Re: How to link both start and finish dates to different tasks

Quote:
Originally Posted by terrymarkham View Post
Is it possible to have the start date of a task be based on a predessor AND have the finish date be based on a different task. I want MS Project to calc the duration based on 2 different tasks.
Hi Terry,

It sounds like a Hammock Task would suit your needs.

See:

http://support.microsoft.com/kb/141733

I hope this helps.
Julie
Reply With Quote
  #4  
Old 02-12-2011
Member
 
Join Date: Dec 2011
Posts: 3
Re: How to link both start and finish dates to different tasks

Yep...that worked great. Thanks alot for the info.
Reply With Quote
  #5  
Old 03-12-2011
Member
 
Join Date: Dec 2006
Posts: 489
Re: How to link both start and finish dates to different tasks

You're welcome and thanks for the feedback.
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "How to link both start and finish dates to different tasks"
Thread Thread Starter Forum Replies Last Post
MS-Project > Linked tasks, but dates dont' move BefuddledSearcher Windows Software 2 30-01-2012 07:27 PM
Changing Start & Finish Dates akbar Microsoft Project 3 14-04-2010 11:33 PM
Task Start & Finish dates Antonio00 Microsoft Project 6 17-03-2009 09:48 PM
Finish to Finish tasks GoldStein Microsoft Project 2 30-01-2009 09:22 PM
Understanding Project tasks and dates Javan Windows Software 2 05-09-2008 11:32 AM


All times are GMT +5.5. The time now is 05:16 AM.