    Report on resource cost

    I have two resources A and B who are allocated to the project. Resource A is fully allocated, Resource B is not fully allocated. Irrespective of whether the resource is loaded or not, I still need to pay them for the entire month (say 160 hours) at the hourly rate. I want to generate a report on the resource cost (irrespective of whether they are allocated or not) for a given duration. How can I do it?

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: Report on resource cost

    The built in reporting in Project will not handle this. Resource costs to Project are calculated by
    (Work * resource standard rate)+(Overtime Work * OT rate)

    You can do calculations in custom fields to multiply task duration by some other value that you specify. However, this will be calculated by Task -- not resource.

    Julie

Similar Threads

  1. Replies: 8
    Last Post: 08-05-2012, 12:46 PM
  2. Need Suggestion for Repairing cost and Replacement cost for BIOS
    By Kaesini in forum Motherboard Processor & RAM
    Replies: 8
    Last Post: 04-02-2012, 12:11 PM
  3. Visual Report - Budget cost report without baseline cost
    By clauz in forum Microsoft Project
    Replies: 4
    Last Post: 04-02-2012, 02:09 AM
  4. Cash Flow Report Total Cost Does Not Match Gantt Total Cost?
    By kaorisdad in forum Microsoft Project
    Replies: 5
    Last Post: 26-08-2011, 06:50 AM
  5. MS Project Cost per resource in Gantt View
    By Projectproject in forum Windows Software
    Replies: 1
    Last Post: 20-04-2011, 06:27 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,500,679.89713 seconds with 17 queries