|
| ||||||||||
| Tags: microsoft project, project manager, task manager |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| Microsoft Project - Project - Trying to Show Resource Allocation
I'm trying to show the allocation percentage a member is on a certain project. For example, Kevin may be 50% on shipping and 50 % on packaging the first week of Nov. and on second week of Nov. he is 75% on shipping and 25% on packaing. Ideally, I want to be able to indicate this on the Team Planner view with the allocation percentage amount right on the bars and to be able to see the % change each week if there is change. I want to be able to label a single bar with multiple percentages to show the allocation change.. when it changes and the project change. Please advise on how I can do this or if not... an alternative? I want to be able to show this visually. Many thanks in advance. |
|
#2
| |||
| |||
| Re: Microsoft Project - Project - Trying to Show Resource Allocation
Not sure much about your issue, I hope that following links can help you out to find appropriate solution. There are number of other help options on the same link which have more better solutions. Percent (%) Allocation fields View resource workloads and availability |
|
#3
| |||
| |||
| Re: Microsoft Project - Project - Trying to Show Resource Allocation
Hello thisistony, I'm afraid the Team Planner view has very little in the way of customization available. My suggestion is to use the Resource Usage view and add Peak Usage to the right side. This should show you assignment units per assignment. Zoom out to view a weekly basis. You may also find the "remaining availability" field is helpful. I hope this helps. Julie |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Microsoft Project - Project - Trying to Show Resource Allocation" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Resource Allocation and Units not adding up correctly for Duration Base Project Management | ndfspeed1971 | Microsoft Project | 4 | 26-03-2012 07:59 PM |
| Distributing resource allocation from desktop Project 2010 | bobofgold | Microsoft Project | 6 | 23-03-2012 10:40 AM |
| Format the project in Microsoft Project | Ground 0 | Tips & Tweaks | 4 | 07-12-2010 06:23 AM |
| Microsoft Project show Percentage of Total Cost | gammaxi1282 | Windows Software | 1 | 13-08-2009 09:11 AM |
| Resource Allocation in Microsoft Project | Manik | Microsoft Project | 4 | 26-04-2009 12:15 PM |