Microsoft Project - Project - Trying to Show Resource Allocation

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 24-11-2011
Member
 
Join Date: Nov 2011
Posts: 1
Microsoft Project - Project - Trying to Show Resource Allocation

Hi All,

I'm trying to show the allocation percentage a member is on a certain project.

For example, Kevin may be 50% on shipping and 50 % on packaging the first week of Nov. and on second week of Nov. he is 75% on shipping and 25% on packaing.

Ideally, I want to be able to indicate this on the Team Planner view with the allocation percentage amount right on the bars and to be able to see the % change each week if there is change. I want to be able to label a single bar with multiple percentages to show the allocation change.. when it changes and the project change.

Please advise on how I can do this or if not... an alternative? I want to be able to show this visually.

Many thanks in advance.

Reply With Quote
  #2  
Old 26-11-2011
Member
 
Join Date: Aug 2011
Posts: 538
Re: Microsoft Project - Project - Trying to Show Resource Allocation

Not sure much about your issue, I hope that following links can help you out to find appropriate solution. There are number of other help options on the same link which have more better solutions.

Percent (%) Allocation fields

View resource workloads and availability
Reply With Quote
  #3  
Old 28-11-2011
Member
 
Join Date: Dec 2006
Posts: 479
Re: Microsoft Project - Project - Trying to Show Resource Allocation

Hello thisistony,

I'm afraid the Team Planner view has very little in the way of customization available.

My suggestion is to use the Resource Usage view and add Peak Usage to the right side. This should show you assignment units per assignment. Zoom out to view a weekly basis.

You may also find the "remaining availability" field is helpful.

I hope this helps.
Julie
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: , ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Microsoft Project - Project - Trying to Show Resource Allocation"
Thread Thread Starter Forum Replies Last Post
Resource Allocation and Units not adding up correctly for Duration Base Project Management ndfspeed1971 Microsoft Project 4 26-03-2012 07:59 PM
Distributing resource allocation from desktop Project 2010 bobofgold Microsoft Project 6 23-03-2012 10:40 AM
Format the project in Microsoft Project Ground 0 Tips & Tweaks 4 07-12-2010 06:23 AM
Microsoft Project show Percentage of Total Cost gammaxi1282 Windows Software 1 13-08-2009 09:11 AM
Resource Allocation in Microsoft Project Manik Microsoft Project 4 26-04-2009 12:15 PM


All times are GMT +5.5. The time now is 07:00 PM.