Thread: Automatically change duration from days to weeks

  1. #1
    Join Date
    Mar 2010
    Posts
    57

    Automatically change duration from days to weeks

    I have a (big) schedule with all the durations in days. Now the PM wants to see the durations in weeks. Do I have to manually change each duration, or is there a way to do it automatically?

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: Automatically change duration from days to weeks

    Hi Martin,

    Run the "Format Duration" macro. Tools > Macro > Macros. Select the Format_Duration macro and when it runs, select weeks.

    I hope this helps.
    Julie

  3. #3
    Join Date
    Mar 2010
    Posts
    57

    Re: Automatically change duration from days to weeks

    Thank you! That was so easy! It is amazing all the things Project can do. You just have to know where to find them.

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: Automatically change duration from days to weeks

    You're most welcome and thanks for the feedback.

  5. #5
    Join Date
    Nov 2011
    Posts
    1

    Re: Automatically change duration from days to weeks

    Sorry for bringing this old thread back up but does anyone know how to do this same thing in Project 2010 now that there are no default macros like referenced above?

    Thanks,
    Ed

  6. #6
    Join Date
    Dec 2006
    Posts
    489

    Re: Automatically change duration from days to weeks

    If you change the "duration is entered in" setting that should alter the duration measurement for the Duration1 field. Create a formula in the Duration1 field of [Duration] and you can now see the information formatted correctly.

    Julie

Similar Threads

  1. Change Work field default to change hours, not duration?
    By Dharitree in forum Microsoft Project
    Replies: 6
    Last Post: 03-11-2009, 03:58 AM
  2. find period in days / hours excluding weekdays between two days?
    By Segvoia in forum Software Development
    Replies: 3
    Last Post: 19-06-2009, 11:17 AM
  3. How to calculate duration in days
    By aileen in forum Microsoft Project
    Replies: 3
    Last Post: 26-09-2008, 08:28 PM
  4. Duration shown in days(need) to display hours
    By The Man in forum Microsoft Project
    Replies: 0
    Last Post: 23-09-2008, 05:26 PM
  5. duration calculation doesn't skip non-working days
    By Donald in forum Microsoft Project
    Replies: 3
    Last Post: 24-01-2008, 05:12 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,558,242.23064 seconds with 17 queries