Thread: Work days from Actual Start vs Baseline Start

  1. #1
    Join Date
    Mar 2011
    Posts
    2

    Work days from Actual Start vs Baseline Start

    Is there a field showing the Work Days (not calendar days) between a tasks Actual Start date and Baseline Start date. If not, How can I calc the value in a Number field? Thanks in advance.

  2. #2
    Join Date
    Mar 2011
    Posts
    2

    Re: Work days from Actual Start vs Baseline Start

    I found the solution. If you enter this formula in one of your number columns, it will provide you the duration (not including weekends and holidays).

    ProjDateDiff(Baseline Start,Start)/480

Similar Threads

  1. Converting work days to calendar days
    By TheTurner in forum Microsoft Project
    Replies: 12
    Last Post: 02-07-2014, 10:15 PM
  2. Replies: 3
    Last Post: 22-07-2009, 11:11 PM
  3. Replies: 3
    Last Post: 21-07-2009, 05:23 PM
  4. start/Run, start/Search, and start/Help and Support not working
    By Debbie in Plano in forum Windows XP Support
    Replies: 7
    Last Post: 18-04-2007, 11:08 AM
  5. Replies: 3
    Last Post: 24-11-2006, 11:00 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,558,460.32925 seconds with 17 queries