Originally Posted by
J_R12
Hey Everyone,
So I've noticed this seems to be a reoccurring problem, but I have NO idea what's going on with my schedule. For some reason project is calculating the duration for longer than it should be. See the example below.
2.06 days Mon 10/17/11 8:00 AM Tue 10/18/11 2:30 AM
2.16 days Mon 10/17/11 8:00 AM Tue 10/18/11 3:24 AM
Now I know that it does it based on the start and stop times of the summary line and not the sum of subtasks, which is what you see above. Obviously Monday 8am to tuesday at 3:00am is not 2 days. I have no resources assigned and the calendar is 24 hours so there should be no restraints. Any advice here?
Thank you.