| Formula to calculate date of delivery
If possible is it able to calculate when we need to order 4 weeks before the start date for that task and for it to be on a specific day on that week i.e thursday. Thankyou |
|
#2
| |||
| |||
| Re: Formula to calculate date of delivery
Try this as a start: Create a task called say "Order items" and give it a durration of zero to make it a milestone. In its predecessor column enter the ID of your work task, make it start-start and give it a lead of 20 days (it should look then something like 35SS-20d). Project will then calculate the date that you should order the items but it may not be a Thursday (sorry but cant help with that). |
|
#3
| |||
| |||
| Re: Formula to calculate date of delivery
Shoppingboy got you 99% there with a start to start and a lead on the task. Then create a calendar with the only working day set to all Thursdays. If you give the "Order Items" task a duration of anything greater than zero (perhaps 10 minutes to place the call) and assign the custom calendar to the task, you should be all set. The lead places the task a minimum of the lead days before -- the custom calendar will force it to schedule only on Thursday. I hope this helps. Julie |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Formula to calculate date of delivery" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Need a formula to calculate years/days/months among several date in Excel | Kumar esan | MS Office Support | 2 | 16-02-2012 07:05 PM |
| How to calculate formula as per run rate in Excel | (Cowherd) | MS Office Support | 2 | 15-02-2012 03:58 PM |
| I am looking for a formula to calculate compound interest in Excel | Corey Dunnett | MS Office Support | 3 | 03-02-2012 05:05 PM |
| Need a simple formula to calculate EV and PV seperately | CooRa | Microsoft Project | 2 | 17-09-2009 10:16 PM |
| Changing start date and creating formula for finish date | stringse | Microsoft Project | 1 | 11-09-2006 01:13 PM |