    Cash Flow Report Total Cost Does Not Match Gantt Total Cost?

    Can someone tell my why my Cash Flow Report total does not match the Total Cost shown in the Gantt View of my project? I use MS Project 2003. I ran a Cash Flow Report from View/Reports/Costs/Cash Flow and my project total shows a total that is different from the Total Cost.

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: Cash Flow Report Total Cost Does Not Match Gantt Total Cost?

    Pretty tough to tell without some more details. I am guessing you are comparing the Total Cost field at the Project Summary task line to the last page of the Cost report?

    Have you customized the report in any way? The default format is to show "Costs" -- is it possible you are seeing remaining or actual costs?

    Feel free to attached the file (you'll need to zip I believe) and I'll take a look.

  3. #3
    Join Date
    Aug 2011
    Posts
    3

    Re: Cash Flow Report Total Cost Does Not Match Gantt Total Cost?

    Yes, when I look at the Total Cost on the Gantt View of my project, it shows an amount different than the last page of the Cash Flow Report. They should be the same.

    I have not customized the report. The report attributes are:

    Row: Resources, and
    Column: Cost
    Filter: All Resources

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: Cash Flow Report Total Cost Does Not Match Gantt Total Cost?

    You are looking at two different things. If you report shows "Resources" you are looking a cash flow for resources. If you look at the Gantt chart, you are seeing Task costs.

    Do you have fixed costs assigned to any tasks? Apply the Cost table and look for fixed costs -- they will NOT appear in resource costs.

    Apply the cost table to the Resource Sheet and add all costs there -- do they match the report?

  5. #5
    Join Date
    Aug 2011
    Posts
    3

    Re: Cash Flow Report Total Cost Does Not Match Gantt Total Cost?

    THANK YOU!! I do have fixed costs. I had rolled up my activities and I have assumed that the fixed costs would show in the rolled up total.

    I see why my total wasn't adding up.

    Thanks for your help!

  6. #6
    Join Date
    Dec 2006
    Posts
    489

    Re: Cash Flow Report Total Cost Does Not Match Gantt Total Cost?

    Glad to have helped and thanks for the feedback.

    Julie

Similar Threads

  1. Need Suggestion for Repairing cost and Replacement cost for BIOS
    By Kaesini in forum Motherboard Processor & RAM
    Replies: 8
    Last Post: 04-02-2012, 12:11 PM
  2. Visual Report - Budget cost report without baseline cost
    By clauz in forum Microsoft Project
    Replies: 4
    Last Post: 04-02-2012, 02:09 AM
  3. Report on resource cost
    By jamespaul.tg in forum Microsoft Project
    Replies: 1
    Last Post: 03-12-2011, 05:37 PM
  4. MS Project Cost per resource in Gantt View
    By Projectproject in forum Windows Software
    Replies: 1
    Last Post: 20-04-2011, 06:27 PM
  5. Microsoft Project show Percentage of Total Cost
    By gammaxi1282 in forum Windows Software
    Replies: 1
    Last Post: 13-08-2009, 09:11 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,689,680.75799 seconds with 17 queries