why does the visual budget cost report inflate costs?
I want to assign a cost to a construction task that has an 86 day duration from 9/30/11 - 1/27/12.
The cost should start accruing (prorated) 2 months after the start of the construction task...so I created a seperate construction expense task and connected it by the predecessor to the construction task (assume the expense task is 27, so predecessor is 27SS+2 mons.
I then assigned a fixed cost to the expense task of $3M.
to see the prorated costs I used the visual report/budget cost report.
what I got was inflated costs....looking at the assignment usage worksheet in the excel workbook I found:
costs start 4Q11, week 21 = 34,883
22-25 = 174,418, but week 26 (end of quarter) jump up to spend the rest???
26 = 2,267,441... Q4 totals 2,99,999.98...!!!???
1Q12 continues!
Week 27-38 = 174,418, which give Q1 a total of 2,09,023!!!???
I notice that the 'offending' week 26, $2,267,441 happens to be the prorated amount of 174,418 + the 1Q12 total of 2,093,023...??.. coincidence?....
HELP!
Bookmarks