Originally Posted by
kubatn
My problem is that when I update the Baseline for individual task, after adding resource to that particular task, "Baseline Cost" for tasks (in Task Sheet view) is updated, but "Baseline Cost" for resources (in Resource Sheet view) is not updated (stays at 0.00$) and I cannot calculate PV(BCWS) for Earned Value analysis. I am using Microsoft Project 2010.
I have a project that already has a baseline and some tracking. Initially, some of the tasks were not assigned resources and thus do not have values such as "Baseline Cost". Now, I would like to update the baseline in order to use Effective Value fields/calculations.
This is what I did:
1)Create resource
2)Assign resource to the task
3)Update baseline by selecting the task and going to "Set Baseline/Selected tasks". Click OK.
This is what I get:
In task sheet - Baseline Cost is updated
In resource sheet - Baseline Cost is O$ (and PV stays 0$)
I tested this in a new project and same thing happens. If I do "Set baseline/Set Baseline" (i.e. use a brand new baseline) "Baseline Cost" in resources changes and I can use various Earned Value calculations. But this is unacceptable, because i will lose all the baseline data for other tasks.
I'm not sure if this is a glitch or may be I'm doing something wrong.
Thanks in advance for help!
Bookmarks