Hi,
I'm sorry but I will have to ask another basic question. I was given an Excel spreadsheet with two columns: Start Date and Finish Date. Since the entries were over 100 rows long I thought to just copy and paste each column into its related column in MS Project. Problem is, MS project keeps changing the dates. It doesn't recognize 4/24/11 to 4/25/11 as being 1 (one) day. Similarly a date range in Excel of 4/21/11 to 12/30/11 is converted to 6/28/11 - 12/30/11 for some reason. To compound this, in my company, Saturday and Sunday are working days.
How can I set up Project to accept what is cut/pasted? I don't want to manually fix each entry.
Thank you.