Changing Calendar to count all days and not only BUSINESS days

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 11-01-2011
Member
 
Join Date: Dec 2010
Posts: 5
Changing Calendar to count all days and not only BUSINESS days

My project has reports that are due a specific number of days prior to and post an event. On the Gantt Chart I want to show in the "Duration" colum the number of days that the report is due, but my days keep changing on the task that has the test event. For example, I have a test event 2/7-2/14, I have a Test Readiness Review due 14 days prior to the start of the test and a Test Plan due 45 days prior to the start of the test. I would like to show the 14 days and 45 days, respectively, on the Gantt Chart, but when I make them Predecessors to the test event my dates change on the test task. Can I change the Calendar to count all days and not only business days?

Reply With Quote
  #2  
Old 11-01-2011
Member
 
Join Date: Jan 2006
Posts: 2,255
Re: Changing Calendar to count all days and not only BUSINESS days

You can add a start to start link between test readiness review and test. Then add a -14ed lead to push the test readiness review 14 calendar days before the test task. Double click on the link line and enter the -14ed in the lag field. The "ed" stands for elapsed days and counts 24 hour periods of time -- disregarding working and nonworking time set in the calendar.
Reply With Quote
  #3  
Old 11-01-2011
Member
 
Join Date: Dec 2010
Posts: 5
Re: Changing Calendar to count all days and not only BUSINESS days

That worked for me. Thank you very much for your time and for sharing your experience.
Reply With Quote
  #4  
Old 12-01-2011
Member
 
Join Date: Jan 2006
Posts: 2,255
Re: Changing Calendar to count all days and not only BUSINESS days

You're welcome and thanks for the feedback.
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: , ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Changing Calendar to count all days and not only BUSINESS days"
Thread Thread Starter Forum Replies Last Post
Calendar days vs work days Boerseun Microsoft Project 4 02-07-2014 11:28 PM
Converting work days to calendar days TheTurner Microsoft Project 12 02-07-2014 11:15 PM
MS Project Calendar days MSPLearnerOz Microsoft Project 5 28-09-2011 06:35 PM
find period in days / hours excluding weekdays between two days? Segvoia Software Development 3 19-06-2009 12:17 PM
How do I use DATEDIFF to count only working days? HAYES Microsoft Project 2 24-06-2008 05:46 PM


All times are GMT +5.5. The time now is 01:56 PM.