Successor task starts on same day predecessor task ends

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 11-10-2010
Member
 
Join Date: Oct 2010
Posts: 1
Successor task starts on same day predecessor task ends

Hi there,

I've noticed the start date on my tasks which have a Finish to Start relationship with their predecessors, start on the same date the predecessor task ends.

eg.

Task Nm Duration Start Finish pred resource
task 1 1 day Mon 11/10/10 Tue 12/10/10 person 2
task 2 1 day Tue 12/10/10 Tue 12/10/10 1 person 2
task 3 4 days Wed 13/10/10 Mon 18/10/10 2 person 2
task 4 2 days Mon 18/10/10 Wed 20/10/10 3 person 2

what I want is for the sucessor task to start the day after the predecessor ends

e.g


Task Nm Duration Start Finish pred resource
task 1 1 day Mon 11/10/10 Mon 11/10/10 person 2
task 2 1 day Tue 12/10/10 Tue 12/10/10 1 person 2
task 3 4 days Wed 13/10/10 Mon 18/10/10 2 person 2
task 4 2 days Tue 19/10/10 Wed 20/10/10 3 person 2


Any idea's ?

Thanks

Reply With Quote
  #2  
Old 01-05-2011
Member
 
Join Date: May 2008
Posts: 3,524
Re: Successor task starts on same day predecessor task ends

You need to check out a couple of things first, are there resource(s) assigned to the sucessor task? Do they have any non-working time in their calendars? Under Tools>Options on the calculation page is your calculation set to automatic? Is the time from between the tasks set as non working in the project calendar? Hope these ideas help. Let us know how you get along.
Reply With Quote
  #3  
Old 03-01-2014
Member
 
Join Date: Aug 2011
Posts: 454
Re: Successor task starts on same day predecessor task ends

That can be due to improper task dependency. When you start a project execution the project life is determined on its own. It is essential that you must go ahead with proper planing before beginning. Or else there can be complicated issues later on. For more reference I am giving you a link that offer proper details on choosing the correct type of dependency. So just checkout the article once.

Choose the right type of task dependency
Reply With Quote
  #4  
Old 03-01-2014
Member
 
Join Date: Aug 2011
Posts: 539
Re: Successor task starts on same day predecessor task ends

You can use Microsoft Project more properly if you are able to understand how task work in it. How to configure duration and go ahead with managing task dependencies. It is not possible to paste everything here in detail. There is a link available which everything properly mentioned. You can on that basis configure the task back again.

Task settings that affect how tasks are scheduled
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags: ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Successor task starts on same day predecessor task ends"
Thread Thread Starter Forum Replies Last Post
Windows Scheduled Task: Unable to start task. 0x80070005: Access is denied. BCU_AJones Windows Software 3 17-01-2014 09:37 AM
Reschedule task if its predecessor ends early? DavidD33 Microsoft Project 11 09-05-2012 08:34 PM
Windows 7 x64: Error message ‘task backgroundconfigsurveyor:The task image is corrupt’ Angee Windows x64 Edition 7 31-07-2011 05:47 PM
When computer starts no task bar start menu or Icons show-up jwarren Operating Systems 7 14-04-2009 09:24 PM
How to Audit Predecessor and Successor Relationships in Project Plan? chupparustam Microsoft Project 3 07-04-2008 05:52 AM


All times are GMT +5.5. The time now is 12:40 PM.