When updating tasks in Microsoft Project 2007, how can I configure it so that if a predecessor is completed early the task that follows it is rescheduled?
In the past if I complete a task before its due date I usually just click the "100% Complete" button on the tracking toolbar. In order to have successors and the tracking gantt update I have been changing the finish date to be the current day's date— is this the best method?
Thanks,
David