Custom Field to display start time in Hours and Minutes

Hey guys, am in urgent need of some help regarding Microsoft Project. Now I have been working with MSP since past couple of months but am not able to find a way to display the start time field in hours and minutes. So far Iíve tried using Custom field but it displays one or the other. In other attempt I tried contact both but it gives me an error message in the field. Somebody please help me out.

Reply With Quote
  #2  
Old 01-06-2010
Member
 
Join Date: Sep 2004
Posts: 150
Re: Custom Field to display start time in Hours and Minutes

You havenít mentioned which MSP project you are using, I mean 2003 or 2007. Anyways, in Project 2007, I need to go to Tools > Options > View and select the Date Format on top of the list. After doing this I get all dates including time of day. So you can go through the same and see if t works for you as well.
Reply With Quote
  #3  
Old 01-06-2010
Member
 
Join Date: Oct 2004
Posts: 39
Re: Custom Field to display start time in Hours and Minutes

Thank you very much for the help buddy, but mine is Project 2010?
Reply With Quote
  #4  
Old 20-04-2012
Member
 
Join Date: Apr 2012
Posts: 1
Re: Custom Field to display start time in Hours and Minutes

Hi,

I've recently created a new 'View' in my Project where I can have numerous different columns open ready to export data to Excel for reporting and inputting to Pivot Tables. My problem is, I want to maintain my date format in my Gantt chart view with the day in front of the date, but want just straight date format in my new 'View', does anyone know if it's possible to have 2 different date formats in the same project?
Reply With Quote
  #5  
Old 20-04-2012
Member
 
Join Date: Dec 2006
Posts: 479
Re: Custom Field to display start time in Hours and Minutes

You can over-ride date formats in views in the table definition. Edit the table and select a different date format in the lower portion of the dialog.

I hope this helps.

Julie
Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Tags:



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Custom Field to display start time in Hours and Minutes"
Thread Thread Starter Forum Replies Last Post
Project 2007 - Custom working hours rstuart Windows Software 1 14-10-2011 11:49 AM
MSP custom field formula to track project progress M0m1 Microsoft Project 1 30-04-2011 03:40 AM
Nautilus - display size and field name Remedy Windows Software 5 11-01-2010 11:46 AM
Change Work field default to change hours, not duration? Dharitree Microsoft Project 6 03-11-2009 02:58 AM
Project Duration measured in hours and minutes Kuval Microsoft Project 2 09-10-2009 02:22 PM


All times are GMT +5.5. The time now is 04:44 PM.