    Custom Field to display start time in Hours and Minutes

    Hey guys, am in urgent need of some help regarding Microsoft Project. Now I have been working with MSP since past couple of months but am not able to find a way to display the start time field in hours and minutes. So far I’ve tried using Custom field but it displays one or the other. In other attempt I tried contact both but it gives me an error message in the field. Somebody please help me out.

  2. #2
    Join Date
    Sep 2004
    Posts
    150

    Re: Custom Field to display start time in Hours and Minutes

    You haven’t mentioned which MSP project you are using, I mean 2003 or 2007. Anyways, in Project 2007, I need to go to Tools > Options > View and select the Date Format on top of the list. After doing this I get all dates including time of day. So you can go through the same and see if t works for you as well.

  3. #3
    Join Date
    Oct 2004
    Posts
    39

    Re: Custom Field to display start time in Hours and Minutes

    Thank you very much for the help buddy, but mine is Project 2010?

  4. #4
    Join Date
    Apr 2012
    Posts
    1

    Re: Custom Field to display start time in Hours and Minutes

    Hi,

    I've recently created a new 'View' in my Project where I can have numerous different columns open ready to export data to Excel for reporting and inputting to Pivot Tables. My problem is, I want to maintain my date format in my Gantt chart view with the day in front of the date, but want just straight date format in my new 'View', does anyone know if it's possible to have 2 different date formats in the same project?

  5. #5
    Join Date
    Dec 2006
    Posts
    489

    Re: Custom Field to display start time in Hours and Minutes

    You can over-ride date formats in views in the table definition. Edit the table and select a different date format in the lower portion of the dialog.

    I hope this helps.

    Julie

Similar Threads

  1. Project 2007 - Custom working hours
    By rstuart in forum Windows Software
    Replies: 1
    Last Post: 14-10-2011, 11:49 AM
  2. MSP custom field formula to track project progress
    By M0m1 in forum Microsoft Project
    Replies: 1
    Last Post: 30-04-2011, 03:40 AM
  3. Nautilus - display size and field name
    By Remedy in forum Windows Software
    Replies: 5
    Last Post: 11-01-2010, 12:46 PM
  4. Change Work field default to change hours, not duration?
    By Dharitree in forum Microsoft Project
    Replies: 6
    Last Post: 03-11-2009, 03:58 AM
  5. Project Duration measured in hours and minutes
    By Kuval in forum Microsoft Project
    Replies: 2
    Last Post: 09-10-2009, 02:22 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,678,852.17421 seconds with 17 queries