Results 1 to 5 of 5

Thread: how to use Baseline

  1. #1
    Join Date
    Oct 2005
    Posts
    30

    how to use Baseline

    Hello Microsoft MVPs, I have a very short query and hope you can help me out. I just wanted to know how can we use Baseline in Microsoft Project? It will appreciated if someone explain it with an example. Thank you very much.

  2. #2
    Join Date
    May 2006
    Posts
    2,812
    Once you developed the phase of your schedule, just save the baseline. After this whenever you will update this schedule to reflect the changes, it will show you where you are now compared to where you said you should be. In simple words, it means you have to move tasks to when they actually started and finished.

  3. #3
    Join Date
    Aug 2010
    Posts
    2

    Re: how to use Baseline

    I am having problems showing my baseline vs the current project status. I have experimented with several things, but in general, I thought the procedure should be:

    set up project tasks and associated durations and links
    save a baseline
    start updating tasks
    view tracking gantt

    At this point, should I not see both the current task bars (red or blue) as well as the original baseline in black? The chart rearranges itself to allow space for the baseline, but those spaces are empty. Can someone guide me as to where I am going wrong?

    Also, in some cases, we actually beat the planned timing. What is the correct way to adjust the schedule to reflect this?

    Any assistance would be appreciated,

    Andrew

  4. #4
    Join Date
    Dec 2007
    Posts
    1,599

    Re: how to use Baseline

    Hi gtv630,

    You can try to check that there's nothing preventing the task starting at 0800 on the first day. Maybe a predecessor doesn't finish until 0900, or perhaps your calendar is not set to begin at 0800 or Tool/Options/Calendar is not set to 0800. Try Tools/Options.../View tab and select a Duration format that has the time showing. Is it 0600? In your real project, I would be inclined to delete the task and re-enter it. If, as you have done, you change the working times in Tools/Options... this will not affect what has happened in the past, only for the future - so re-entering the task should do the trick.

  5. #5
    Join Date
    Aug 2010
    Posts
    2

    Re: how to use Baseline

    I think I have everything working now. Perhaps I was setting Baseline 1, instead of just setting the baseline. The software seems very particular as to what order you do things as well. Thanks.

Similar Threads

  1. Copying baseline
    By mbbackus in forum Microsoft Project
    Replies: 4
    Last Post: 15-12-2011, 07:47 PM
  2. Display baseline for Summary task
    By sa02000 in forum Microsoft Project
    Replies: 5
    Last Post: 25-10-2011, 08:04 PM
  3. Replies: 5
    Last Post: 24-08-2011, 03:41 AM
  4. How to draw a graph of the cost baseline?
    By hindustnidude in forum Microsoft Project
    Replies: 3
    Last Post: 27-05-2008, 01:07 AM
  5. How to revise Baseline in Microsoft Project
    By prafullanayana in forum Microsoft Project
    Replies: 2
    Last Post: 25-03-2008, 05:33 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,416,316.13741 seconds with 17 queries