Thread: Need Help, Task Start Date wrong

  1. #1
    Join Date
    Oct 2005
    Posts
    46

    Need Help, Task Start Date wrong

    I have created few Tasks in MSP 2007 linked with finish to start. In this Task i manually set date to schedule from, hours per day set to 8 and Working Monday thru Friday. Going in details, the schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10.

    Here if you will notice instead of 6/7/10 Task2 should have a Start Date of 6/8/10, right? Any idea what went wrong behind this? Please help me to fix it.

  2. #2
    Join Date
    Oct 2004
    Posts
    1,342

    Re: Need Help, Task Start Date wrong

    Can you try to turn on the display of time. Just go to Tools > Options, View tab and select a format that shows time as well as date. It might help to figure out what is the issue here. Also you have mentioned that you have the standard setting hours per day of 8. So, did you try to modify the calendar in Tools > Change Working time?

  3. #3
    Join Date
    Sep 2005
    Posts
    208

    Re: Need Help, Task Start Date wrong

    After checking I saw that display of time shows start 8am and finish 8am on the next day for a 1 day duration task. And yeah, I have modified the calendar in Tools > Options, calendar tab to 7:00am to 12:00pm 12:30pm to 3:30pm. When I checked the Start dates then it is still showing on same date as predecessors finish date. I cant say why start time is 8am and finish time is 8am on next day for 1 day task?

  4. #4
    Join Date
    Oct 2004
    Posts
    1,342
    The settings you change under Tools > Options > Calendar, for the working week or day affect the way project views your entries in the duration field. If you type in 1 week, Project looks to the setting you've made to define the number of hours (and thus man-hours) that a week contains. Ditto for the working day. Check for more tips here - http://project.mvps.org/faqs.htm#Def...orking%20Hours

  5. #5
    Join Date
    Jun 2011
    Posts
    1

    Re: Need Help, Task Start Date wrong

    duration Start Time Finish Time
    0.63 hrs June 3, 2011 11:42 AM June 3, 2011 1:20 PM

    Sir these are the timings of my task and the duration should be 1 hour . something but ms project is showing .63 hr as above. plz help!!!!

  6. #6
    Join Date
    Nov 2009
    Posts
    1,035

    Re: Need Help, Task Start Date wrong

    i woudl like to suggest you to turn on the display of time and after that go through your isssue. to do thid go to the tools and under that make click on the option. now on the option tab go to the View tab and under that select the format and that shows the time and date. i hope this will help you.

  7. #7
    Join Date
    Dec 2006
    Posts
    489

    Re: Need Help, Task Start Date wrong

    Quote Originally Posted by fahad.hashmi View Post
    duration Start Time Finish Time
    0.63 hrs June 3, 2011 11:42 AM June 3, 2011 1:20 PM

    Sir these are the timings of my task and the duration should be 1 hour . something but ms project is showing .63 hr as above. plz help!!!!
    The hour from 12:00 pm to 1:00 pm is likely non-working. So, you have 18 minutes of working time from 11:42 to 12:00 and 20 minutes of working time from 1:00 pm to 1:20 pm. The calculation is correct.

    Check your calendar definitions and if the resources work through the lunch hour, you'll need to change the calendar to reflect different working hours.

    I hope this helps.
    Julie

Similar Threads

  1. Replies: 3
    Last Post: 17-01-2014, 10:37 AM
  2. No desktop icons, task manager, mouse or task bar on start up
    By night-13 in forum Operating Systems
    Replies: 2
    Last Post: 07-12-2011, 10:44 PM
  3. Task Start Date does not match constraint
    By ctslaton in forum Microsoft Project
    Replies: 2
    Last Post: 17-09-2011, 04:57 AM
  4. Can project send email reminder of task start date?
    By Dilbert in forum Microsoft Project
    Replies: 3
    Last Post: 01-06-2011, 10:55 PM
  5. Changing start date and creating formula for finish date
    By stringse in forum Microsoft Project
    Replies: 1
    Last Post: 11-09-2006, 01:13 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,563,195.71687 seconds with 16 queries