I have got one question about Microsoft Project. I have made a project plan and I have set the baseline also. Now I just want to show the delay of each task, so can anyone tell me how to do that? Lets say for example, one of the task started on march 20, 2010 and is suppose to finish on march 23, 2010. The task started normally on time but finished on March 30 same year? So, how can I show the delay of this gap days in the project plan. Thanks.