Thread: Need help to access Current Date filter on Microsoft Project

  1. #1
    Join Date
    May 2010
    Posts
    65

    Need help to access Current Date filter on Microsoft Project

    I need some help to work with Project 2007. I am not able to setup a filter on the same that can allow me to view a set of task that has finished at interval of 30 days. In that what are the possible ways available through which I can simply access current date and configure filters on it. It would allow me to get more details on the older task and calculate a time difference.

  2. #2
    Join Date
    May 2010
    Posts
    1
    There is on Current Date field provided. So that is the reason you cannot get any ste of filter for the same. But you can do one thing. You can try to add custom date that might work and set the formula as per your choice. You can start working with a filter with the help of date field and you can then add the value in the same. Try the same and then provide information what error you got or you had able to get right result.

  3. #3
    Join Date
    Sep 2004
    Posts
    105

    re: Need help to access Current Date filter on Microsoft Project

    Julie's proposal will work just fine. I might propose a slightly different approach:

    1) Take a spare Duration field and add the following formula: ProjDateDiff([Current Date],[Finish],[Task Calendar GUID]) - this will calculate the difference between the Current Date and the Finish date for the task. Swap out Baseline Finish for Finish if required.

    2) Create a new Group (Project > Group By), that groups by the custom Duration field. Set the intervals to 30.

    That should do it. You may want to filter out completed tasks using a filter (Project > Filter for).

  4. #4
    Join Date
    Mar 2012
    Posts
    3

    re: Need help to access Current Date filter on Microsoft Project

    [QUOTE=JulieS;4906035]The [Current Date] field is not available in the value choice
    options for custom filters. However, you could add a custom date
    field (Date10 for example) and set the formula for that field as
    [Current date].

    Then create the filters using the date field as the value.



    I tried creating a formula for current date as described above but there was a syntax error. can you please provide the specific formula. thanks.

  5. #5
    Join Date
    Dec 2006
    Posts
    489

    re: Need help to access Current Date filter on Microsoft Project

    The formula is:

    [Current Date]

    no equal sign and field name enclosed in square brackets.

    What did you enter?

  6. #6
    Join Date
    Mar 2012
    Posts
    3

    re: Need help to access Current Date filter on Microsoft Project

    I entered date 5 = [Current date]

  7. #7
    Join Date
    Mar 2012
    Posts
    3

    re: Need help to access Current Date filter on Microsoft Project

    Thanks Juile it worked fine.

    How do I show incomplete tasks due in 5 days from current Date? thanks.

  8. #8
    Join Date
    Dec 2006
    Posts
    489

    re: Need help to access Current Date filter on Microsoft Project

    You're welcome and thanks for the feedback.

    Have you looked at the built in Date Range filter? It allow you to specify and start and finish date dynamically.

    To get the current date + 5 working days - change your Date5 formula to:

    DateAdd("d",5,[Start])

    Julie

  9. #9
    Join Date
    Mar 2010
    Posts
    57

    re: Need help to access Current Date filter on Microsoft Project

    This is great! I will try both suggestions since I currently run the "Should start/finish by" filter, put in the dates for 30, then 60, then 90 days from now. Then I have to go through and manually weed out the 30 dayers from the 60-day list and the 30 and 60 dayers from the 90-day list with another filter. Luckily my schedules are fairly short and statused frequently enough that there aren't many each time.
    This will definitely be easier!

  10. #10
    Join Date
    Dec 2006
    Posts
    489

    re: Need help to access Current Date filter on Microsoft Project

    Have you thought about using grouping on the date fields? You can set intervals to see your tasks grouped by day or by week

  11. #11
    Join Date
    Mar 2010
    Posts
    57

    re: Need help to access Current Date filter on Microsoft Project

    That is so easy! You should write a book! You always have the best ideas.

  12. #12
    Join Date
    Dec 2006
    Posts
    489

    re: Need help to access Current Date filter on Microsoft Project

    Thanks very much for your enthusiastic feedback. I actually have written a book about MS Project as well as MS Project and Clarity. Sadly, they were for clients so they are not available at your favorite bookstore.

  13. #13
    Join Date
    Mar 2010
    Posts
    57

    re: Need help to access Current Date filter on Microsoft Project

    Bummer.
    I'm actually looking for a book to improve my skills. I have no idea what all Project can do even though I've been using it for three years now.

    It's funny how other people post questions that I have been pondering, too.

    I was looking in the Kindle store yesterday, but they have so few. They are so expensive, too, so I don't want to buy one and find out it's garbage.

Similar Threads

  1. Replies: 5
    Last Post: 23-04-2011, 10:19 PM
  2. How to add SilverLight 3 on current ASP.NET 2.0 web project.
    By Andre Patton in forum Technology & Internet
    Replies: 4
    Last Post: 18-04-2011, 07:55 PM
  3. How to cross-site access to Microsoft Project?
    By Miquel in forum Windows Software
    Replies: 3
    Last Post: 11-11-2010, 01:25 AM
  4. MS Project 2007 Current date column
    By shoppingboy in forum Windows Software
    Replies: 3
    Last Post: 21-05-2010, 12:40 AM
  5. Getting Current Date in Java
    By Level8 in forum Software Development
    Replies: 5
    Last Post: 27-02-2010, 05:26 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,614,000.31830 seconds with 17 queries