Though am working with MS Project from past few months but this is the first time am going to load a schedule with resources. So being a newbie I need some help. One of my clients who is a constructor wants me to do this. It is having a large schedule in projects, and want me to "resource load" this. If possible, I want to know how can I load each task by quantity. Note that there are over 100 tasks with which I need to do this.
Let me give a quick detail about my task: I will need 1 foreman, 10 operators and 6 labors working 3 days to complete this task plus all relevant equipment. According to this now can anyone please tell me the easiest and proper method to enter this without entering "operator" 10 times for each task?