    How to remove weekends (Sat & Sun) in Project?

    Hi,

    I need to remove weekends in my Gantt Chart and show working days only (Mon - Fri).

    How can you do this in Project?

    Thanks.

  2. #2
    Join Date
    May 2006
    Posts
    2,335

    Re: How to remove weekends (Sat & Sun) in Project?

    Hello conks,

    Welcome to the Project newsgroup. Sorry, you cannot hide the display of Saturday and Sunday in the Gantt chart view. You can show a "5 day" week in the Calendar view.

    I hope this helps. Let us know how you get along.

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. Replies: 3
    Last Post: 10-11-2010, 07:27 PM
  3. Replies: 1
    Last Post: 20-08-2010, 01:27 AM
  4. Microsoft Project not counting weekends - Saturday and Sunday
    By Dhananjay in forum Microsoft Project
    Replies: 3
    Last Post: 13-03-2009, 11:43 AM
  5. How do I convert Project 2007 document to open in Project 2003?
    By nehal_serpa in forum Microsoft Project
    Replies: 6
    Last Post: 31-10-2007, 03:12 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,556,484.62825 seconds with 17 queries