I have got a task with a 5d duration and 5d of work. When I complete only part of my work each day, then my duration and finish date should grow accordingly. I have checked both Move check boxes in tools > options > calculate. There are actually 4 move check boxes but I have checked just the 2 that are at the top level. In day 1, I have completed only 0.5d of work. This moves my completion date 0.5d ahead. I have then set my current date and status date in Project > Information to the next calendar date. On my second day, I have completed only 0.5d of work and my completion date pushes the duration of the task ahead another 0.5d which will make my duration field equal to 6d but the duration field remains at 5d. When I do only 0.5d of work each day, then my task duration should grow from 5d to 10d but instead of that my duration field remains at 5d and my final SV is 0. I dont know why the duration will not grow and my SV does not reflect a blown schedule? Thanks for any information.
Bookmarks