Go Back   TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Become a Member!
Forgot your username/password?
Register Tags Active Topics RSS Search Mark Forums Read SiteMap

Tags: , , ,

Sponsored Links



Summary Task Percent Complete Incorrect

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 21-10-2009
mikejw
 
Posts: n/a
Summary Task Percent Complete Incorrect

Hello,

I have several groupings that have a summary task and 10 milestones (0
duration) underneath. At the moment, 8 of those milestones have been
completed, 2 are incomplete, however, the percent complete on their summary
task is showing 0%. Playing around, I noticed that if I change the duration
from 0 to 1, the corrrect percent complete shows up at the summary level.

Can someone help me understand why the summary task's percent complete is
not being updated as task below it complete?

Thank you,

MikeW
Reply With Quote
  #2  
Old 21-10-2009
Trevor Rabey
 
Posts: n/a
Re: Summary Task Percent Complete Incorrect

Everyone who has ever used MSP notices this and the question pops up in the
group at frequent, regular intervals.
Then everyone tries to explain about how milestones are just "punctuation",
not real tasks, so progress of nothing is nothing, and overall progress of a
bunch of nothings is nothing.
Also, the Summary progress calculation does the best it can but there are so
many different ways to combine, link and overlap tasks and milestones under
a Summary, and so many ways that they can all be not started, in progress or
finished, that no one is ever really happy that Summary progress looks
right.
It's an average of the % Complete of what's done, or something like that but
so what? I don't even remember the exact algorithm without testing and
checking examples. Someone will.

My point is, it's irrelevant, and there is no point in puzzling over it
because Summary % Complete has no useful meaning, no matter how it is
arrived at.
It is certainly no indicator of anything connected with progress or
performance, and it does not provide any clue about what should be done.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"mikejw" <mikejw@discussions.microsoft.com> wrote in message
news:E4482B20-F029-4611-859C-2A731CADF8B0@microsoft.com...
> Hello,
>
> I have several groupings that have a summary task and 10 milestones (0
> duration) underneath. At the moment, 8 of those milestones have been
> completed, 2 are incomplete, however, the percent complete on their
> summary
> task is showing 0%. Playing around, I noticed that if I change the
> duration
> from 0 to 1, the corrrect percent complete shows up at the summary level.
>
> Can someone help me understand why the summary task's percent complete is
> not being updated as task below it complete?
>
> Thank you,
>
> MikeW



Reply With Quote
  #3  
Old 21-10-2009
Jonathan Sofer [MVP]
 
Posts: n/a
Re: Summary Task Percent Complete Incorrect

% Complete is based on duration so that makes sense. It can't determine the
% complete unless all the milestones are complete at which point the summary
will show 100%.

Jonathan

"mikejw" <mikejw@discussions.microsoft.com> wrote in message
news:E4482B20-F029-4611-859C-2A731CADF8B0@microsoft.com...
> Hello,
>
> I have several groupings that have a summary task and 10 milestones (0
> duration) underneath. At the moment, 8 of those milestones have been
> completed, 2 are incomplete, however, the percent complete on their
> summary
> task is showing 0%. Playing around, I noticed that if I change the
> duration
> from 0 to 1, the corrrect percent complete shows up at the summary level.
>
> Can someone help me understand why the summary task's percent complete is
> not being updated as task below it complete?
>
> Thank you,
>
> MikeW


Reply With Quote
  #4  
Old 21-10-2009
vanita
 
Posts: n/a
RE: Summary Task Percent Complete Incorrect

Hi MikeW

% complete is based on duration and is connected with the data in the two
columns of 'Actual Duration' and 'Remaining duration'. For milestones these
data are 0 so consolidated % complete for Summary tasks would also be 0.

If for each milestone completion you want to show 10% complete, i.e with 8
milestones complete, Summary task should show 80% complete you may insert a
Text column e.g Text1 and for Summary tasks you may yourself input data
accordingly in that column. You may also customise the Gantt area to show
Text1 data alongwith the bars.

I hope it helps.
Vanita
--
Project Management consultant and trainer
vanita_ahuja@yahoo.com



"mikejw" wrote:

> Hello,
>
> I have several groupings that have a summary task and 10 milestones (0
> duration) underneath. At the moment, 8 of those milestones have been
> completed, 2 are incomplete, however, the percent complete on their summary
> task is showing 0%. Playing around, I noticed that if I change the duration
> from 0 to 1, the corrrect percent complete shows up at the summary level.
>
> Can someone help me understand why the summary task's percent complete is
> not being updated as task below it complete?
>
> Thank you,
>
> MikeW

Reply With Quote
  #5  
Old 21-10-2009
Jim Aksel
 
Posts: n/a
RE: Summary Task Percent Complete Incorrect

This behavior is by design. If the subtasks under a summary task are all
milestones (0 duration) then summary %Complete remains at 0% until all
subtask milestones are completed. This is to avoid a division by 0 problem.

Although I do not specifically cover this case, if you read my white paper
on my blog you will see how %Complete is calculated (it is weighted by
duration). In your case, the sum of all the durations is still 0 which is
what creates the problem. Should you be so inclined, visit the link below,
select Project Tips and then hunt for the white paper on Percent Complete
which explains how it is calculated.

Strangely enough, 0/0 in mathmatical terms is 1 by definition (or at best is
indeterminate). What you seek is a count of complete milestones divided by
total number of milestones. You would have to do that in two custom number
fields with formulas and then divide the results at the summary level.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"mikejw" wrote:

> Hello,
>
> I have several groupings that have a summary task and 10 milestones (0
> duration) underneath. At the moment, 8 of those milestones have been
> completed, 2 are incomplete, however, the percent complete on their summary
> task is showing 0%. Playing around, I noticed that if I change the duration
> from 0 to 1, the corrrect percent complete shows up at the summary level.
>
> Can someone help me understand why the summary task's percent complete is
> not being updated as task below it complete?
>
> Thank you,
>
> MikeW

Reply With Quote
  #6  
Old 21-10-2009
Trevor Rabey
 
Posts: n/a
Re: Summary Task Percent Complete Incorrect

Jim, there is no chance that 0/0 even exists let alone is equal to 1.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Jim Aksel" <JimAksel@discussions.microsoft.com> wrote in message
news:5B5A1A2F-4347-4C0F-8E0B-A64B0CE9FF4B@microsoft.com...
> This behavior is by design. If the subtasks under a summary task are all
> milestones (0 duration) then summary %Complete remains at 0% until all
> subtask milestones are completed. This is to avoid a division by 0
> problem.
>
> Although I do not specifically cover this case, if you read my white paper
> on my blog you will see how %Complete is calculated (it is weighted by
> duration). In your case, the sum of all the durations is still 0 which is
> what creates the problem. Should you be so inclined, visit the link
> below,
> select Project Tips and then hunt for the white paper on Percent Complete
> which explains how it is calculated.
>
> Strangely enough, 0/0 in mathmatical terms is 1 by definition (or at best
> is
> indeterminate). What you seek is a count of complete milestones divided
> by
> total number of milestones. You would have to do that in two custom
> number
> fields with formulas and then divide the results at the summary level.
> --
> If this post was helpful, please consider rating it.
>
> Jim Aksel, MVP
>
> Check out my blog for more information:
> http://www.msprojectblog.com
>
>
>
> "mikejw" wrote:
>
>> Hello,
>>
>> I have several groupings that have a summary task and 10 milestones (0
>> duration) underneath. At the moment, 8 of those milestones have been
>> completed, 2 are incomplete, however, the percent complete on their
>> summary
>> task is showing 0%. Playing around, I noticed that if I change the
>> duration
>> from 0 to 1, the corrrect percent complete shows up at the summary level.
>>
>> Can someone help me understand why the summary task's percent complete is
>> not being updated as task below it complete?
>>
>> Thank you,
>>
>> MikeW



Reply With Quote
  #7  
Old 21-10-2009
Jim Aksel
 
Posts: n/a
Re: Summary Task Percent Complete Incorrect

Yes, it is a strange one. There are two competing math rules at play.

1. Any number divided by itself is 1
2. Any number divided by 0 is infinity.

Since this doesn't make sense, it certainly is indeterminate.

We'll leave it to the math PhDs to reconcile. It will give them something
to do :)

Jim

_______________

"Trevor Rabey" wrote:

> Jim, there is no chance that 0/0 even exists let alone is equal to 1.
> --
> Trevor Rabey
> 0407213955
> 61 8 92727485
> PERFECT PROJECT PLANNING
> www.perfectproject.com.au
>
> "Jim Aksel" <JimAksel@discussions.microsoft.com> wrote in message
> news:5B5A1A2F-4347-4C0F-8E0B-A64B0CE9FF4B@microsoft.com...
> > This behavior is by design. If the subtasks under a summary task are all
> > milestones (0 duration) then summary %Complete remains at 0% until all
> > subtask milestones are completed. This is to avoid a division by 0
> > problem.
> >
> > Although I do not specifically cover this case, if you read my white paper
> > on my blog you will see how %Complete is calculated (it is weighted by
> > duration). In your case, the sum of all the durations is still 0 which is
> > what creates the problem. Should you be so inclined, visit the link
> > below,
> > select Project Tips and then hunt for the white paper on Percent Complete
> > which explains how it is calculated.
> >
> > Strangely enough, 0/0 in mathmatical terms is 1 by definition (or at best
> > is
> > indeterminate). What you seek is a count of complete milestones divided
> > by
> > total number of milestones. You would have to do that in two custom
> > number
> > fields with formulas and then divide the results at the summary level.
> > --
> > If this post was helpful, please consider rating it.
> >
> > Jim Aksel, MVP
> >
> > Check out my blog for more information:
> > http://www.msprojectblog.com
> >
> >
> >
> > "mikejw" wrote:
> >
> >> Hello,
> >>
> >> I have several groupings that have a summary task and 10 milestones (0
> >> duration) underneath. At the moment, 8 of those milestones have been
> >> completed, 2 are incomplete, however, the percent complete on their
> >> summary
> >> task is showing 0%. Playing around, I noticed that if I change the
> >> duration
> >> from 0 to 1, the corrrect percent complete shows up at the summary level.
> >>
> >> Can someone help me understand why the summary task's percent complete is
> >> not being updated as task below it complete?
> >>
> >> Thank you,
> >>
> >> MikeW

>
>
> .
>

Reply With Quote
  #8  
Old 22-10-2009
Steve House
 
Posts: n/a
Re: Summary Task Percent Complete Incorrect

Adding to the other's comments, a summary task with only milestones as it's
children makes no sense from a schedule standpoint. The project plan is a
detailed model of exactly what ACTIONS have to take place in order to create
the milestones. All you have there is a to-do list. It gives you no
guidance as to what has to happen to achieve your objectives, thus there is
nothing to measure progress towards those objectives against.


--
Steve House
MS Project Trainer & Consultant

"mikejw" <mikejw@discussions.microsoft.com> wrote in message
news:E4482B20-F029-4611-859C-2A731CADF8B0@microsoft.com...
> Hello,
>
> I have several groupings that have a summary task and 10 milestones (0
> duration) underneath. At the moment, 8 of those milestones have been
> completed, 2 are incomplete, however, the percent complete on their
> summary
> task is showing 0%. Playing around, I noticed that if I change the
> duration
> from 0 to 1, the corrrect percent complete shows up at the summary level.
>
> Can someone help me understand why the summary task's percent complete is
> not being updated as task below it complete?
>
> Thank you,
>
> MikeW


Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Summary Task Percent Complete Incorrect"
Thread Thread Starter Forum Replies Last Post
Automatic Percent Complete? trailerpup Microsoft Project 5 09-12-2011 04:32 AM
Project Summary task BCWP is blank in task usage skier9er Microsoft Project 2 19-05-2011 05:49 PM
Reports - showing summary task for each task Floyd5 Microsoft Project 4 14-11-2009 03:45 AM
Summary Task Duration incorrect redmadcap Microsoft Project 4 10-10-2008 08:37 AM
How do you show percent complete on the task form? Phil Microsoft Project 1 17-09-2008 04:18 AM


All times are GMT +5.5. The time now is 10:33 PM.