| Resource Graph - Can you view by "group" rather than "resource"
I have set up a project and assigned resources. These Resources are also members of given groups - assigned in the "resource sheet" view. For example, Joe Smith is in the group "Human Resources" along with Bob Jones, and Ann Williams. I would like to view the resource graph allocation of time by the group "Human Resources" rather than by each individual person. Can this be done? Thanks. |
|
#2
| |||
| |||
| RE: Resource Graph - Can you view by "group" rather than "resource"
Hi, Instead of using the Resource Graph view, you may want to use the "Graphs" button on the Assign Resources dialog box: From a task view, open the dialog box (ALT+F10) and select the resources you want to view, then click on Graphs button. Hope this helps. Best regards, -- José Miguel Piñeres MCITP | MCT San José, Costa Rica http://projectpedia.blogspot.com "Hoosier Daddy" wrote: > I have set up a project and assigned resources. > > These Resources are also members of given groups - assigned in the "resource > sheet" view. For example, Joe Smith is in the group "Human Resources" along > with Bob Jones, and Ann Williams. > > I would like to view the resource graph allocation of time by the group > "Human Resources" rather than by each individual person. > > Can this be done? Thanks. |
|
#3
| |||
| |||
| RE: Resource Graph - Can you view by "group" rather than "resource
I am using MS Project 2000. I don't see this option nor can I find a "graph" view elsewhere "José Miguel Piñeres" wrote: > Hi, > > Instead of using the Resource Graph view, you may want to use the "Graphs" > button on the Assign Resources dialog box: From a task view, open the dialog > box (ALT+F10) and select the resources you want to view, then click on Graphs > button. > > Hope this helps. > > Best regards, > -- > José Miguel Piñeres > MCITP | MCT > San José, Costa Rica > http://projectpedia.blogspot.com > > > "Hoosier Daddy" wrote: > > > I have set up a project and assigned resources. > > > > These Resources are also members of given groups - assigned in the "resource > > sheet" view. For example, Joe Smith is in the group "Human Resources" along > > with Bob Jones, and Ann Williams. > > > > I would like to view the resource graph allocation of time by the group > > "Human Resources" rather than by each individual person. > > > > Can this be done? Thanks. |
|
#4
| |||
| |||
| RE: Resource Graph - Can you view by "group" rather than "resource
Hello, I am sorry, the answer I gave you applies to Microsoft Office Project 2007. Maybe you should consider upgrading since, there are a lot of goodies you are missing. BR -- José Miguel Piñeres MCITP | MCT San José, Costa Rica http://projectpedia.blogspot.com "Hoosier Daddy" wrote: > I am using MS Project 2000. I don't see this option nor can I find a "graph" > view elsewhere > > "José Miguel Piñeres" wrote: > > > Hi, > > > > Instead of using the Resource Graph view, you may want to use the "Graphs" > > button on the Assign Resources dialog box: From a task view, open the dialog > > box (ALT+F10) and select the resources you want to view, then click on Graphs > > button. > > > > Hope this helps. > > > > Best regards, > > -- > > José Miguel Piñeres > > MCITP | MCT > > San José, Costa Rica > > http://projectpedia.blogspot.com > > > > > > "Hoosier Daddy" wrote: > > > > > I have set up a project and assigned resources. > > > > > > These Resources are also members of given groups - assigned in the "resource > > > sheet" view. For example, Joe Smith is in the group "Human Resources" along > > > with Bob Jones, and Ann Williams. > > > > > > I would like to view the resource graph allocation of time by the group > > > "Human Resources" rather than by each individual person. > > > > > > Can this be done? Thanks. |
|
#5
| |||
| |||
| Re: Resource Graph - Can you view by "group" rather than "resource"
This should work. I forget the features in 2000, but I don't think they've changed all that much: http://blogs.catapultsystems.com/epm...rce-graph.aspx - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > I have set up a project and assigned resources. > > These Resources are also members of given groups - assigned in the > "resource sheet" view. For example, Joe Smith is in the group "Human > Resources" along with Bob Jones, and Ann Williams. > > I would like to view the resource graph allocation of time by the > group "Human Resources" rather than by each individual person. > > Can this be done? Thanks. > |
|
#6
| |||
| |||
| Re: Resource Graph - Can you view by "group" rather than "resource"
Hi, See Faq 38 (Combined resource Graph) in http://www.mvps.org/project/faqs.htm Greetings, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Hoosier Daddy" <Hoosier Daddy@discussions.microsoft.com> wrote in message news:83B38C85-4EF3-49B3-BC21-27F8D74495D5@microsoft.com... >I have set up a project and assigned resources. > > These Resources are also members of given groups - assigned in the > "resource > sheet" view. For example, Joe Smith is in the group "Human Resources" > along > with Bob Jones, and Ann Williams. > > I would like to view the resource graph allocation of time by the group > "Human Resources" rather than by each individual person. > > Can this be done? Thanks. |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Resource Graph - Can you view by "group" rather than "resource"" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| cannot open hard disk, error "Access to the resource ‘C:\’ has been disallowed" | eliteraj | Windows XP Support | 1 | 23-06-2011 09:42 PM |
| Windows 7: "Failed to load resource DLL" dialog box | mADiRAkSHii | Operating Systems | 4 | 30-01-2011 06:41 PM |
| DNS Server Error: "Windows can't communicate with the device or resource" | Delightful. | Operating Systems | 3 | 20-01-2011 07:51 PM |
| Extender Resource Monitor reports "System Resources Low" | Ed | MediaCenter | 9 | 24-01-2008 10:27 AM |
| Error "Cluster File Share resource '...' has failed a status check." during defrag | Christian Fässler | Windows Server Help | 4 | 07-06-2007 09:18 PM |