|
| |||||||||
| Tags: calculation, critical |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| Help with critical path calculation
I am using MS Project 2002. I have two tasks: Clean Kitchen; Work: 14 hours; Resource: Tim Clean Bathroom; Work: 16 hours; Resource: Tim But MS Project is showing both tasks starting at the same time, with the critical path of 16 hours. The tasks show Tim using 100% effort and Tim is scheduled to work only 8 hours a day. So why does the task finish in 16 hours and not the expected 30 hours (16+14)? Without creating false dependencies, how do I make sure that Project properly shows 1) that the tasks must be done sequentially, or 2) that Tim's 8-hour work day must be split between these two tasks? In either case, the critical path should show that this project will have a 30-hour duration. Read more: http://www.justanswer.com/questions/...#ixzz0SmlpLTAF |
|
#2
| |||
| |||
| Re: Help with critical path calculation
I have MS Project 2007 and do not have much experience... So, please correct me if I wrong. I think it is because MS Project does not do automatic resource leveling. You have to do that manually. Go to Tools -> Resource Leveling and click Level Now. |
|
#3
| |||
| |||
| Re: Help with critical path calculation
Thanks for your help. I tried that, but going to Tools --> Level Resources --> and clicking "Level Now" does, to all appearances, absolutely nothing. I only have these two tasks in this test project and it's not changing anything. In my real project, it doesn't seem to do anything either, although I've put far too many tasks into that to be absolutely sure. Any other ideas? Thanks so much! |
|
#4
| |||
| |||
| Re: Help with critical path calculation
Either create the dependency - is it not false if it is a dependency and choosing a sequence of work is perfectly valid. Or use resource leveling to level Tim's tasks. Both are reasonable solutions. -Jack Dahlgren "ProjectUser84" <ProjectUser84.3zfnjb@DoNotSpam.com> wrote in message news:ProjectUser84.3zfnjb@DoNotSpam.com... > > I am using MS Project 2002. I have two tasks: Clean Kitchen; Work: 14 > hours; Resource: Tim Clean Bathroom; Work: 16 hours; Resource: Tim But > MS Project is showing both tasks starting at the same time, with the > critical path of 16 hours. The tasks show Tim using 100% effort and Tim > is scheduled to work only 8 hours a day. So why does the task finish in > 16 hours and not the expected 30 hours (16+14)? Without creating false > dependencies, how do I make sure that Project properly shows 1) that the > tasks must be done sequentially, or 2) that Tim's 8-hour work day must > be split between these two tasks? In either case, the critical path > should show that this project will have a 30-hour duration. > |
|
#5
| |||
| |||
| RE: Help with critical path calculation
Not exactly. A couple of things. First, do not confuse work with duration. I can do 2 hours of work in three days of duration. There are columns for each. The critical path is calculating correctly at 2 days because the tasks run in parallel. It is possible for the tasks to be worked concurrently, although we are overloading Tim to do so. We would only want to establish a Finish to Start dependency on the tasks if they could not be worked simultaneously. For example, if the bathroom was a room off the kitchen, it would make sense to clean the bath first then move on to the kitchen... perhaps becuase we had to let the floor dry or something. Notice it is the realationship between the tasks that establishes the dependency, not the fact that Tim is working both. What you have is a resource allocation problem, Tim is overloaded. You can fix that by using Tools/Level Resources... There is more detail about your options there in the help (on the Resource Leveling form). This algorithm will assign Tim to work the tasks sequentially. Under no circumstances does Project reallocate the resource assignmetns among the tasks. If you assigned Tim at 100% he will stay that way. If you want the taks to work concurrently and have Tim split his time, you will have to do that manually. Here is how. In the Gantt view, select Window/Split... you now have two windows with the work assignments at the bottom. You will see Tim is allocated at 100%. Change that to 50% and the duration will doulble. Do the same thing for the other task. Now, Tim works 50% on each task for twice as long and the length of your critical path changes. If the two tasks are differing amounts of work (and therefore duration), project will not automactically increase Tim's allocation to 100% once the first task is done. If he was assigned at 50% he will stay there. Project is not smart enough to know you want to keep Tim gainfully employed at 100% if possible. That would be a nice feature, perhaps in Project 2012... In your case, the project will show a critical path of a duration that depends on the resource assignments. If Tim has help from Bob, the duration will be 2 days. If Tim works solo the duration is (almost) four days if you level Tim as a resource. If Tim is not leveled, the tasks run in parallel and the correct critical path duration is two days. If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "ProjectUser84" wrote: > > I am using MS Project 2002. I have two tasks: Clean Kitchen; Work: 14 > hours; Resource: Tim Clean Bathroom; Work: 16 hours; Resource: Tim But > MS Project is showing both tasks starting at the same time, with the > critical path of 16 hours. The tasks show Tim using 100% effort and Tim > is scheduled to work only 8 hours a day. So why does the task finish in > 16 hours and not the expected 30 hours (16+14)? Without creating false > dependencies, how do I make sure that Project properly shows 1) that the > tasks must be done sequentially, or 2) that Tim's 8-hour work day must > be split between these two tasks? In either case, the critical path > should show that this project will have a 30-hour duration. > > Read more: > http://www.justanswer.com/questions/...#ixzz0SmlpLTAF > > > -- > ProjectUser84 > ------------------------------------------------------------------------ > ProjectUser84's Profile: http://forums.techarena.in/members/140480.htm > View this thread: Help with critical path calculation > > http://forums.techarena.in > > |
|
#6
| |||
| |||
| Re: Help with critical path calculation
Thanks Jim, I had that thought too. Unfortunately, the tasks are not running concurrently and Tim is not overallocated. For some reason it only considers the second task critical. When I assign a start date to the first task, both tasks become critical. This seems like it solves the problem, right? Sadly, when I add a third task that only Tim can do, it gets inserted into the middle of my first two tasks and is not considered critical, although the first and third task both still are critical. What do you think that might be all about? It certainly seems to defy any logic I can think of. Thanks for all your help. |
|
#7
| |||
| |||
| Re: Help with critical path calculation
Hi, Sorry, how can you say that Tim is not overallocated if he is planned to do two tasks in parallel, each at 100%? Use Resource leveling to resolve the overallocation rather than denying it :-)) Greetings, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "ProjectUser84" <ProjectUser84.3zft3a@DoNotSpam.com> wrote in message news:ProjectUser84.3zft3a@DoNotSpam.com... > > Thanks Jim, > > I had that thought too. Unfortunately, the tasks are not running > concurrently and Tim is not overallocated. For some reason it only > considers the second task critical. When I assign a start date to the > first task, both tasks become critical. This seems like it solves the > problem, right? > > Sadly, when I add a third task that only Tim can do, it gets inserted > into the middle of my first two tasks and is not considered critical, > although the first and third task both still are critical. What do you > think that might be all about? It certainly seems to defy any logic I > can think of. > > Thanks for all your help. > > > -- > ProjectUser84 > ------------------------------------------------------------------------ > ProjectUser84's Profile: http://forums.techarena.in/members/140480.htm > View this thread: Help with critical path calculation > > http://forums.techarena.in > |
|
#8
| |||
| |||
| Re: Help with critical path calculation
Jan, You caught me! I was trying to conceal the fact that Tim is going to be cleaning the kitchen and the bathroom at the same time! I DIDN'T WANT ANYONE TO KNOW! Just kidding! I know that Tim is not doing both of these tasks at the same time because I am looking at the Gantt chart and it clearly shows that he is doing one task, and then doing the other - not both at the same time. I have used resource leveling. It does not solve the problem. |
|
#9
| |||
| |||
| Re: Help with critical path calculation
It may not show the "right" critical path but it does put the tasks in a feasible order .. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "ProjectUser84" <ProjectUser84.3zg1fc@DoNotSpam.com> wrote in message news:ProjectUser84.3zg1fc@DoNotSpam.com... > > Jan, > > You caught me! I was trying to conceal the fact that Tim is going to > be cleaning the kitchen and the bathroom at the same time! I DIDN'T WANT > ANYONE TO KNOW! > > Just kidding! > > I know that Tim is not doing both of these tasks at the same time > because I am looking at the Gantt chart and it clearly shows that he is > doing one task, and then doing the other - not both at the same time. > > I have used resource leveling. It does not solve the problem. > > > -- > ProjectUser84 > ------------------------------------------------------------------------ > ProjectUser84's Profile: http://forums.techarena.in/members/140480.htm > View this thread: Help with critical path calculation > > http://forums.techarena.in > |
|
#10
| |||
| |||
| Re: Help with critical path calculation
You are not being a naughty boy and keying in dates are you? It seems we've shifted the question. First you were saying Tim works both concurrently, now he does not but your critical path is still a mess. Sorry, I am confused. Might you care to donate the file jeaksel at yahoo dot com -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "ProjectUser84" wrote: > > Jan, > > You caught me! I was trying to conceal the fact that Tim is going to > be cleaning the kitchen and the bathroom at the same time! I DIDN'T WANT > ANYONE TO KNOW! > > Just kidding! > > I know that Tim is not doing both of these tasks at the same time > because I am looking at the Gantt chart and it clearly shows that he is > doing one task, and then doing the other - not both at the same time. > > I have used resource leveling. It does not solve the problem. > > > -- > ProjectUser84 > ------------------------------------------------------------------------ > ProjectUser84's Profile: http://forums.techarena.in/members/140480.htm > View this thread: Help with critical path calculation > > http://forums.techarena.in > > |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Help with critical path calculation" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Critical path breaksup | lalit715 | Microsoft Project | 2 | 1 Week Ago 03:20 PM |
| Critical Path | emq_33@hotmail.com | Microsoft Project | 7 | 24-03-2009 06:05 AM |
| Critical Path Analysis | NH Ralph | Microsoft Project | 3 | 09-12-2008 03:43 AM |
| critical path problems | swell estimator | Microsoft Project | 3 | 26-10-2008 10:47 AM |
| critical path reference | johnston | Microsoft Project | 2 | 12-10-2008 10:56 PM |