|
| |||||||||
| Tags: actual, complete, planned |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| Planned vs Actual Work and % complete
Hi All I am playing around with MS Project having taken a break. I've set up a basic test schedule with 5 tasks, selected task type duration, unselected effort driven. I've including 3 additional fields in my basic gant view - work, actual work and % complete. I have tasks of a fixed duration e.g. I have a 4 hour task that will take a 2 day duration. When I populate the actual work field the % complete changes and I'd expect this. However, what if I have a task with a duration of 2 days, 5 hours per day but the resource completes the task on day 2 in 3 hours. This would mean that the planned hours were 10 hours, the actuals were 8 and the % complete is 100% leaving 2 hours as an underspend/time saved. Is there a method to model this scenario? Many thanks to everyone who takes the time to read & respond. Cheers, H |
|
#2
| |||
| |||
| RE: Planned vs Actual Work and % complete
You may enter actual work, remaining work, and remaining duration in the columns containing those names. In your specific case, set remaining work and remaining duration to 0. This will set %complete to 100% and produce cost and schedule variances (in this case a good thing). I have a white paper on my blog that addresses some of these issues. See the link below -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "Hardip" wrote: > Hi All > > I am playing around with MS Project having taken a break. I've set up a > basic test schedule with 5 tasks, selected task type duration, unselected > effort driven. > > I've including 3 additional fields in my basic gant view - work, actual work > and % complete. I have tasks of a fixed duration e.g. I have a 4 hour task > that will take a 2 day duration. > > When I populate the actual work field the % complete changes and I'd expect > this. However, what if I have a task with a duration of 2 days, 5 hours per > day but the resource completes the task on day 2 in 3 hours. This would mean > that the planned hours were 10 hours, the actuals were 8 and the % complete > is 100% leaving 2 hours as an underspend/time saved. > > Is there a method to model this scenario? > > Many thanks to everyone who takes the time to read & respond. > > Cheers, H > > |
|
#3
| |||
| |||
| Re: Planned vs Actual Work and % complete
You might try a couple of things: 1) Add the Remaining Work column. When the Actual Work = 8, zero out the Remaining Work column. This will set the task to 100% Complete. 2) Consider tracking by % Work Complete and not % Complete. 3) If you're entering timephased work data, consider entering that in the Resource or Task Usage view. Simply right click on the table to the right, and add Actual Work. Then you can enter how many hours a day each resource works. Add Remaining Work to the table at the left, and zero it out when the work is completed. You're basic issue is that it sounds like you're trying to track timephased data in a non-timephased interface. The Gantt Chart doesn't allow you to specify when the work happens, it just smears it out across the task. Task or Resource Usage are the only views that allow you to plug in hours on specific days. -A > Hi All > > I am playing around with MS Project having taken a break. I've set up > a basic test schedule with 5 tasks, selected task type duration, > unselected effort driven. > > I've including 3 additional fields in my basic gant view - work, > actual work and % complete. I have tasks of a fixed duration e.g. I > have a 4 hour task that will take a 2 day duration. > > When I populate the actual work field the % complete changes and I'd > expect this. However, what if I have a task with a duration of 2 > days, 5 hours per day but the resource completes the task on day 2 in > 3 hours. This would mean that the planned hours were 10 hours, the > actuals were 8 and the % complete is 100% leaving 2 hours as an > underspend/time saved. > > Is there a method to model this scenario? > > Many thanks to everyone who takes the time to read & respond. > > Cheers, H > |
|
#4
| |||
| |||
| Re: Planned vs Actual Work and % complete
Hardip, After entering the Actual Work (5h on day 1 and 3h on day 2) in the Task Usage or Resource Usage view, set the Remaining Work to zero. Hope this helps, -- Gérard Ducouret [Project MVP] www.pragmasoft.fr Un livre sur Project Server 2007 pour le Chef de projet: http://www.lmet.fr/advsearch.cgi?_EX...NCE=10&_PAGE=1 "Hardip" <Hardip@discussions.microsoft.com> a écrit dans le message de news: 5C8C5C21-A0FC-4A7A-B505-519EF1A4FC65@microsoft.com... > Hi All > > I am playing around with MS Project having taken a break. I've set up a > basic test schedule with 5 tasks, selected task type duration, unselected > effort driven. > > I've including 3 additional fields in my basic gant view - work, actual > work > and % complete. I have tasks of a fixed duration e.g. I have a 4 hour task > that will take a 2 day duration. > > When I populate the actual work field the % complete changes and I'd > expect > this. However, what if I have a task with a duration of 2 days, 5 hours > per > day but the resource completes the task on day 2 in 3 hours. This would > mean > that the planned hours were 10 hours, the actuals were 8 and the % > complete > is 100% leaving 2 hours as an underspend/time saved. > > Is there a method to model this scenario? > > Many thanks to everyone who takes the time to read & respond. > > Cheers, H > > |
|
#5
| |||
| |||
| Re: Planned vs Actual Work and % complete
Your question has a lot of detail about what you did, but some of what you did is not relevant to your question. Task Type and Effort Driven, foe example. When you show and hide columns/fields, be aware that you are not changing the View. You are changing the Entry Table. Since the Entry Table is part of the View (but only one of the ingredients) I guess you can say that you are changing the View, but indirectly. You are better off switching to the Tracking Table, which already has the columns/fields that you want, and leave the Entry Table with the original selection and arrangement of columns/fields. Especially, the Tracking Table has the Actual Start and Actual Finish fields and since these are the two most relevant facts you can put these in first (with the time as well as the date). MSP is primarily a scheduling tool, being mainly about durations, predecessors and dates, and Work and Cost are secondary extensions to the basic idea. Actual Work is a historical fact as well and has to be correct, but in your example will be taken care of automatically when you first provide the actual dates. I prefer to always populate the schedule data first, and attend to the actual Work afterwards in the Task Usage and/or Resource Usage Views. You have gained 2 hours, that is 2 Hours of Work and 2 Hours of Duration but they are different things (although both measured in Hours), and that they both equal 2 is just a coincidence. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "Hardip" <Hardip@discussions.microsoft.com> wrote in message news:5C8C5C21-A0FC-4A7A-B505-519EF1A4FC65@microsoft.com... > > Hi All > > I am playing around with MS Project having taken a break. I've set up a > basic test schedule with 5 tasks, selected task type duration, unselected > effort driven. > > I've including 3 additional fields in my basic gant view - work, actual > work > and % complete. I have tasks of a fixed duration e.g. I have a 4 hour task > that will take a 2 day duration. > > When I populate the actual work field the % complete changes and I'd > expect > this. However, what if I have a task with a duration of 2 days, 5 hours > per > day but the resource completes the task on day 2 in 3 hours. This would > mean > that the planned hours were 10 hours, the actuals were 8 and the % > complete > is 100% leaving 2 hours as an underspend/time saved. > > Is there a method to model this scenario? > > Many thanks to everyone who takes the time to read & respond. > > Cheers, H > > |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Planned vs Actual Work and % complete" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| How to get the Actual% complete vs Planned % complete in MS Projects? | JayeshN | Microsoft Project | 1 | 25-12-2011 01:05 AM |
| Showing planned vs actual | Michael Gwin | Microsoft Project | 9 | 01-10-2009 03:47 AM |
| Planned vs. Actual | nickc | Microsoft Project | 5 | 11-04-2009 09:42 AM |
| Decimal rounding issue when actual work greater than planned. | Binoy | Microsoft Project | 3 | 07-10-2008 03:41 PM |
| Capture Actual work when a task is complete | DWall | Microsoft Project | 2 | 18-07-2008 07:38 AM |