MS PRoject Calculation

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 06-06-2009
Shahriar Nour Khondokar
 
Posts: n/a
MS PRoject Calculation

Work Actual Remain Work Baseline
Work Work Variance Work
Project Summary 715.02 482.5 232.5 80.77 634.25
362 289.75 72.25 48.25
2.5 2.5 0 0.75
80.75 70 10.75 13.5
82.75 82.75 0 -4.25
31.75 30.75 1 23.75
3.25 3.25 0 -1.75
3.5 3.5 0 0.5
3 0 3 0
1 0 1 0
8 0 8 0
2.75 0 2.75 0
5 0 5 0
8 0 8 0
3.75 0 3.75 0
1.5 0 1.5 0
1.75 0 1.75 0
1.5 0 1.5 0
2.25 0 2.25 0
6 0 6 0
10 0 10 0
52 0 52 0
3.5 0 3.5 0
3 0 3 0
9 0 9 0
11.5 0 11.5 0
5.5 0 5.5 0
1.5 0 1.5 0
8 0 8 0

Sum calculated
manually 715 482.5 232.5 80.75


Here is a description of the data shown above:
- Topmost row is the project summary row as seen in my project plan (.mpp)
file
- 1st column: Work column; updated automatically when Actual Work is
entered. 2nd column: Actual Work values entered. 3rd column: Remaining Work
calculated automatically. 4th Column: Work Variance calculated automatically
using Baseline Work (total baseline work currently is 634.25).
- The last row is the sum of the values in the rows above it (without the
Project Summary row) which I have calculated manually.

Here is my question:
As you can see above, Project Summary column for Work is .02 greater than
the value calculated manually. This than affects the Work Variance column:
715.02 - 634.25 = 80.77

We enter Work/time values in .25hr slots ie. data will always end with 0,
..25, .5, .75 and nothing else. Hence, .02 or .77 makes my plan file appear
erroneous though I cant find any errors and that's what is shown by the
manual calculations.

So, can someone explain why is MS Project adding .02 at the end of Summary
Work value?
Is there anything I can do so that this does not happen?

Thanks for your help.
Reply With Quote
  #2  
Old 09-06-2009
Jack Dahlgren
 
Posts: n/a
RE: MS PRoject Calculation

It is rounding error equivalent to approximately 1 second. I'd ignore it as
it is meaningless. I'd argue everything to the right of the decimal point is
meaningless.

-Jack Dahlgren


"Shahriar Nour Khondokar" wrote:

> Work Actual Remain Work Baseline
> Work Work Variance Work
> Project Summary 715.02 482.5 232.5 80.77 634.25
> 362 289.75 72.25 48.25
> 2.5 2.5 0 0.75
> 80.75 70 10.75 13.5
> 82.75 82.75 0 -4.25
> 31.75 30.75 1 23.75
> 3.25 3.25 0 -1.75
> 3.5 3.5 0 0.5
> 3 0 3 0
> 1 0 1 0
> 8 0 8 0
> 2.75 0 2.75 0
> 5 0 5 0
> 8 0 8 0
> 3.75 0 3.75 0
> 1.5 0 1.5 0
> 1.75 0 1.75 0
> 1.5 0 1.5 0
> 2.25 0 2.25 0
> 6 0 6 0
> 10 0 10 0
> 52 0 52 0
> 3.5 0 3.5 0
> 3 0 3 0
> 9 0 9 0
> 11.5 0 11.5 0
> 5.5 0 5.5 0
> 1.5 0 1.5 0
> 8 0 8 0
>
> Sum calculated
> manually 715 482.5 232.5 80.75
>
>
> Here is a description of the data shown above:
> - Topmost row is the project summary row as seen in my project plan (.mpp)
> file
> - 1st column: Work column; updated automatically when Actual Work is
> entered. 2nd column: Actual Work values entered. 3rd column: Remaining Work
> calculated automatically. 4th Column: Work Variance calculated automatically
> using Baseline Work (total baseline work currently is 634.25).
> - The last row is the sum of the values in the rows above it (without the
> Project Summary row) which I have calculated manually.
>
> Here is my question:
> As you can see above, Project Summary column for Work is .02 greater than
> the value calculated manually. This than affects the Work Variance column:
> 715.02 - 634.25 = 80.77
>
> We enter Work/time values in .25hr slots ie. data will always end with 0,
> .25, .5, .75 and nothing else. Hence, .02 or .77 makes my plan file appear
> erroneous though I cant find any errors and that's what is shown by the
> manual calculations.
>
> So, can someone explain why is MS Project adding .02 at the end of Summary
> Work value?
> Is there anything I can do so that this does not happen?
>
> Thanks for your help.

Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "MS PRoject Calculation"
Thread Thread Starter Forum Replies Last Post
MS Project calculation of end date kerryger Windows Software 1 15-04-2011 09:11 PM
Project Prof 2007 not opening when new project created in Project Server website GroundLoop Microsoft Project 1 30-01-2011 08:59 AM
Sub-Project - Project Summary Tasks showing on a Master Project Steve Scott Microsoft Project 3 16-01-2009 11:14 PM
% Complete Calculation SwapnaK Microsoft Project 18 17-05-2008 09:17 PM
Microsoft Project crashes when trying to open a project from Project Server bophommarath@yahoo.com Microsoft Project 1 09-05-2005 02:39 PM


All times are GMT +5.5. The time now is 01:13 AM.