|
| |||||||||
| Tags: evms, progress, project, view |
![]() |
| | Thread Tools | Search this Thread |
|
#1
| |||
| |||
| View project progress
Hi, I build my project plan on MSP 2007, and update it with actual work and cost “progress” every two weeks then, save updates (not Save As) every time, is there any way that I can view the status of the project “progress” (Gantt Chart view) and what was the project look like say, one month or two months ago without saving project versions under different files. Advice is highly appreciated. Ammar |
|
#2
| |||
| |||
| Re: View project progress
Hi Ammar, Welcome to this Microsoft Project newsgroup :) There is not a simple method for comparisons. Even if you Save As... to a different name every month, the comparison between the two is not easy. If you don't have a long project, you could re-save the baselines up to 9 times in Project and then put the different baselines on the Tracking Gantt view. To see how this is done, view the Tracking Gantt and Format/Bar Styles... In the dialog, see how the baseline details are entered and then add Baseline1 details underneath. I think you can get 4 lines for each bar. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP See http://tinyurl.com/2xbhc for my free Project Tutorials "Ammar Al-Saket" <AmmarAlSaket@discussions.microsoft.com> wrote in message news:16E618BC-E4B7-4EDB-AC7C-12DC872CB21B@microsoft.com... > Hi, > I build my project plan on MSP 2007, and update it with actual work and > cost > “progress” every two weeks then, save updates (not Save As) every time, is > there any way that I can view the status of the project “progress” (Gantt > Chart view) and what was the project look like say, one month or two > months > ago without saving project versions under different files. > > Advice is highly appreciated. > > Ammar > |
|
#3
| |||
| |||
| Re: View project progress
You could save it on a cyclic basis to the various baseline fields (baseline 1, baseline 2 etc). Partly the answer depends on what it is you want to see. If you have a baseline, you can use the BCWS and BCWP fields and look at the schedule variance for different status dates. Look up earned value if you want to use this technique. Ammar Al-Saket wrote: > Hi, > I build my project plan on MSP 2007, and update it with actual work and cost > “progress” every two weeks then, save updates (not Save As) every time, is > there any way that I can view the status of the project “progress” (Gantt > Chart view) and what was the project look like say, one month or two months > ago without saving project versions under different files. > > Advice is highly appreciated. > > Ammar > |
|
#4
| |||
| |||
| Re: View project progress
Thanks Mike and Dave. In our company we have around 15 PMs, each one of then runs 3-6 short term projects (3-12 months). For future use, our PMs need to save electronic version of project status every month, this includes actual start, actual finish and % complete of each task (Gantt View), so what happens now is that; by the end of the year we will be having hundreds of project plan versions (files) flooding our system, so, I wonder if, in some how, we can have only one plan for each project that includes project status (start, finish and %complete) throughout project implementation. To save Baseline1,2,3,.. is a good solution, but still I can see the progress line in the baseline Bar or % complete associated with that particular Baseline, I went to Format/Bar Styles and select Progress line for Baseline 1,2,3 as relevant but still it doesn’t work properly.. Thanks again Ammar "Dave" wrote: > You could save it on a cyclic basis to the various baseline fields > (baseline 1, baseline 2 etc). > > Partly the answer depends on what it is you want to see. If you have a > baseline, you can use the BCWS and BCWP fields and look at the schedule > variance for different status dates. Look up earned value if you want > to use this technique. > > Ammar Al-Saket wrote: > > Hi, > > I build my project plan on MSP 2007, and update it with actual work and cost > > “progress” every two weeks then, save updates (not Save As) every time, is > > there any way that I can view the status of the project “progress” (Gantt > > Chart view) and what was the project look like say, one month or two months > > ago without saving project versions under different files. > > > > Advice is highly appreciated. > > > > Ammar > > > |
|
#5
| |||
| |||
| Re: View project progress
You're welcome, Ammar :-) However, I don't know of any other way of including routine status. You might consider exporting the important data to Excel where comparisons might be more simple. Mike Glen Project MVP See http://tinyurl.com/2xbhc for my free Project Tutorials "Ammar Al-Saket" <AmmarAlSaket@discussions.microsoft.com> wrote in message news:31EA1D0E-BB98-4E1C-9A87-3D37E8C40185@microsoft.com... > Thanks Mike and Dave. > > In our company we have around 15 PMs, each one of then runs 3-6 short term > projects (3-12 months). For future use, our PMs need to save electronic > version of project status every month, this includes actual start, actual > finish and % complete of each task (Gantt View), so what happens now is > that; > by the end of the year we will be having hundreds of project plan versions > (files) flooding our system, so, I wonder if, in some how, we can have > only > one plan for each project that includes project status (start, finish and > %complete) throughout project implementation. > > To save Baseline1,2,3,.. is a good solution, but still I can see the > progress line in the baseline Bar or % complete associated with that > particular Baseline, I went to Format/Bar Styles and select Progress line > for > Baseline 1,2,3 as relevant but still it doesn’t work properly.. > > Thanks again > Ammar > > > "Dave" wrote: > >> You could save it on a cyclic basis to the various baseline fields >> (baseline 1, baseline 2 etc). >> >> Partly the answer depends on what it is you want to see. If you have a >> baseline, you can use the BCWS and BCWP fields and look at the schedule >> variance for different status dates. Look up earned value if you want >> to use this technique. >> >> Ammar Al-Saket wrote: >> > Hi, >> > I build my project plan on MSP 2007, and update it with actual work and >> > cost >> > “progress” every two weeks then, save updates (not Save As) every time, >> > is >> > there any way that I can view the status of the project “progress” >> > (Gantt >> > Chart view) and what was the project look like say, one month or two >> > months >> > ago without saving project versions under different files. >> > >> > Advice is highly appreciated. >> > >> > Ammar >> > >> |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "View project progress" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Tracking Project Progress | Sam_Sung | Microsoft Project | 10 | 08-12-2011 08:45 PM |
| How to arrange the progress of software project | MaggieK | Software Development | 5 | 03-03-2010 12:09 AM |
| Tracking Project Progress | rooster | Microsoft Project | 4 | 23-06-2009 07:44 PM |
| MS Project 2003; Progress line in a summarybar | Bassiebas15 | Windows Software | 2 | 09-12-2008 05:41 PM |
| Project indicator line (progress??) | andy | Microsoft Project | 6 | 12-11-2008 11:17 AM |