Go Back   TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project
Become a Member!
Forgot your username/password?
Register Tags Active Topics RSS Search Mark Forums Read SiteMap

Tags: , , ,

Sponsored Links



View project progress

Microsoft Project


Reply
 
Thread Tools Search this Thread
  #1  
Old 04-06-2009
Ammar Al-Saket
 
Posts: n/a
View project progress

Hi,
I build my project plan on MSP 2007, and update it with actual work and cost
“progress” every two weeks then, save updates (not Save As) every time, is
there any way that I can view the status of the project “progress” (Gantt
Chart view) and what was the project look like say, one month or two months
ago without saving project versions under different files.

Advice is highly appreciated.

Ammar

Reply With Quote
  #2  
Old 04-06-2009
Mike Glen
 
Posts: n/a
Re: View project progress

Hi Ammar,

Welcome to this Microsoft Project newsgroup :)

There is not a simple method for comparisons. Even if you Save As... to a
different name every month, the comparison between the two is not easy. If
you don't have a long project, you could re-save the baselines up to 9 times
in Project and then put the different baselines on the Tracking Gantt view.
To see how this is done, view the Tracking Gantt and Format/Bar Styles...
In the dialog, see how the baseline details are entered and then add
Baseline1 details underneath. I think you can get 4 lines for each bar.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



"Ammar Al-Saket" <AmmarAlSaket@discussions.microsoft.com> wrote in message
news:16E618BC-E4B7-4EDB-AC7C-12DC872CB21B@microsoft.com...
> Hi,
> I build my project plan on MSP 2007, and update it with actual work and
> cost
> “progress” every two weeks then, save updates (not Save As) every time, is
> there any way that I can view the status of the project “progress” (Gantt
> Chart view) and what was the project look like say, one month or two
> months
> ago without saving project versions under different files.
>
> Advice is highly appreciated.
>
> Ammar
>


Reply With Quote
  #3  
Old 04-06-2009
Dave
 
Posts: n/a
Re: View project progress

You could save it on a cyclic basis to the various baseline fields
(baseline 1, baseline 2 etc).

Partly the answer depends on what it is you want to see. If you have a
baseline, you can use the BCWS and BCWP fields and look at the schedule
variance for different status dates. Look up earned value if you want
to use this technique.

Ammar Al-Saket wrote:
> Hi,
> I build my project plan on MSP 2007, and update it with actual work and cost
> “progress” every two weeks then, save updates (not Save As) every time, is
> there any way that I can view the status of the project “progress” (Gantt
> Chart view) and what was the project look like say, one month or two months
> ago without saving project versions under different files.
>
> Advice is highly appreciated.
>
> Ammar
>

Reply With Quote
  #4  
Old 05-06-2009
Ammar Al-Saket
 
Posts: n/a
Re: View project progress

Thanks Mike and Dave.

In our company we have around 15 PMs, each one of then runs 3-6 short term
projects (3-12 months). For future use, our PMs need to save electronic
version of project status every month, this includes actual start, actual
finish and % complete of each task (Gantt View), so what happens now is that;
by the end of the year we will be having hundreds of project plan versions
(files) flooding our system, so, I wonder if, in some how, we can have only
one plan for each project that includes project status (start, finish and
%complete) throughout project implementation.

To save Baseline1,2,3,.. is a good solution, but still I can see the
progress line in the baseline Bar or % complete associated with that
particular Baseline, I went to Format/Bar Styles and select Progress line for
Baseline 1,2,3 as relevant but still it doesn’t work properly..

Thanks again
Ammar


"Dave" wrote:

> You could save it on a cyclic basis to the various baseline fields
> (baseline 1, baseline 2 etc).
>
> Partly the answer depends on what it is you want to see. If you have a
> baseline, you can use the BCWS and BCWP fields and look at the schedule
> variance for different status dates. Look up earned value if you want
> to use this technique.
>
> Ammar Al-Saket wrote:
> > Hi,
> > I build my project plan on MSP 2007, and update it with actual work and cost
> > “progress” every two weeks then, save updates (not Save As) every time, is
> > there any way that I can view the status of the project “progress” (Gantt
> > Chart view) and what was the project look like say, one month or two months
> > ago without saving project versions under different files.
> >
> > Advice is highly appreciated.
> >
> > Ammar
> >

>

Reply With Quote
  #5  
Old 10-06-2009
Mike Glen
 
Posts: n/a
Re: View project progress

You're welcome, Ammar :-) However, I don't know of any other way of
including routine status. You might consider exporting the important data
to Excel where comparisons might be more simple.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


"Ammar Al-Saket" <AmmarAlSaket@discussions.microsoft.com> wrote in message
news:31EA1D0E-BB98-4E1C-9A87-3D37E8C40185@microsoft.com...
> Thanks Mike and Dave.
>
> In our company we have around 15 PMs, each one of then runs 3-6 short term
> projects (3-12 months). For future use, our PMs need to save electronic
> version of project status every month, this includes actual start, actual
> finish and % complete of each task (Gantt View), so what happens now is
> that;
> by the end of the year we will be having hundreds of project plan versions
> (files) flooding our system, so, I wonder if, in some how, we can have
> only
> one plan for each project that includes project status (start, finish and
> %complete) throughout project implementation.
>
> To save Baseline1,2,3,.. is a good solution, but still I can see the
> progress line in the baseline Bar or % complete associated with that
> particular Baseline, I went to Format/Bar Styles and select Progress line
> for
> Baseline 1,2,3 as relevant but still it doesn’t work properly..
>
> Thanks again
> Ammar
>
>
> "Dave" wrote:
>
>> You could save it on a cyclic basis to the various baseline fields
>> (baseline 1, baseline 2 etc).
>>
>> Partly the answer depends on what it is you want to see. If you have a
>> baseline, you can use the BCWS and BCWP fields and look at the schedule
>> variance for different status dates. Look up earned value if you want
>> to use this technique.
>>
>> Ammar Al-Saket wrote:
>> > Hi,
>> > I build my project plan on MSP 2007, and update it with actual work and
>> > cost
>> > “progress” every two weeks then, save updates (not Save As) every time,
>> > is
>> > there any way that I can view the status of the project “progress”
>> > (Gantt
>> > Chart view) and what was the project look like say, one month or two
>> > months
>> > ago without saving project versions under different files.
>> >
>> > Advice is highly appreciated.
>> >
>> > Ammar
>> >

>>


Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "View project progress"
Thread Thread Starter Forum Replies Last Post
Tracking Project Progress Sam_Sung Microsoft Project 10 08-12-2011 08:45 PM
How to arrange the progress of software project MaggieK Software Development 5 03-03-2010 12:09 AM
Tracking Project Progress rooster Microsoft Project 4 23-06-2009 07:44 PM
MS Project 2003; Progress line in a summarybar Bassiebas15 Windows Software 2 09-12-2008 05:41 PM
Project indicator line (progress??) andy Microsoft Project 6 12-11-2008 11:17 AM


All times are GMT +5.5. The time now is 12:05 AM.