| Updating Task's Finish Date
How do I update a task's finish date? A task in my project will not complete on time. This task is Fixed Duration with 11 resources assigned. 9 of the resources have completed their work, but two resources must continue for another 16 - 24 hours each beyond the scheduled finish date. When I attemp to change the finish date by 3 days, the Project is making many strange changes to all resources remaining work. Also, I've noticed Project changing the task to be 'fixed units'. |
|
#2
| |||
| |||
| Re: Updating Task's Finish Date
When you have multiple Resources on one Task, try this method: Select Window, Split Right mouse-click in the lower pane and select Resource Work Set the Start date to the date the Task actually stated Update Actual and Remaining Work for each Resource. When all remaining work is zero, the Task is complete. -- Rod Gill Microsoft MVP for Project Author of the only book on Project VBA, see: http://www.projectvbabook.com "Tom" <Tom@discussions.microsoft.com> wrote in message news:15CD617B-2F28-432C-8D87-20360C2C16D1@microsoft.com... > How do I update a task's finish date? A task in my project will not > complete > on time. This task is Fixed Duration with 11 resources assigned. 9 of > the > resources have completed their work, but two resources must continue for > another 16 - 24 hours each beyond the scheduled finish date. > > When I attemp to change the finish date by 3 days, the Project is making > many strange changes to all resources remaining work. Also, I've noticed > Project changing the task to be 'fixed units'. |
|
#3
| |||
| |||
| Re: Updating Task's Finish Date
Hi, I like your expression "is making many strange changes" You will now appreciate that in the courses I give I don't even try to explain what can happen if you change the finish date of a task The message is don't like in DO NOT. Enter reality instead - you say it yourself: two resources must continue for > another 16 - 24 hours each beyond the scheduled finish date. That is what you enter (Rod explained how) and LET PROJECT CALCULATE the days. Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Tom" <Tom@discussions.microsoft.com> wrote in message news:15CD617B-2F28-432C-8D87-20360C2C16D1@microsoft.com... > How do I update a task's finish date? A task in my project will not > complete > on time. This task is Fixed Duration with 11 resources assigned. 9 of > the > resources have completed their work, but two resources must continue for > another 16 - 24 hours each beyond the scheduled finish date. > > When I attemp to change the finish date by 3 days, the Project is making > many strange changes to all resources remaining work. Also, I've noticed > Project changing the task to be 'fixed units'. |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Updating Task's Finish Date" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Baseline Column Date automatically updates Finish Date | Adam 1980 | Microsoft Project | 3 | 18-05-2011 07:08 PM |
| Task duration - start set by SF, finish set by FF. Can it be done & how ? | ProjNoob | Windows Software | 3 | 12-08-2009 08:11 PM |
| Lag time between Start-Date and Finish-Date | Shahriar N k | Microsoft Project | 5 | 22-01-2009 09:42 PM |
| Project 2007: Actual Finish Date & Finish | scparker | Microsoft Project | 6 | 08-10-2008 05:53 PM |
| Changing start date and creating formula for finish date | Lisa M | Microsoft Project | 2 | 11-09-2006 06:10 PM |