Highlighting Holidays in the resource view

Hi,

I'm using MS project 2007. We have a central resource plan of which all project plans use. Within this we keep individuals holidays up to date (tools>change working time>"person a">add an exception).

Is there a way to make these holidays clearer in the resouce usage view?

Exceptions from the standard (project calendar) (national holidays, weekends etc) block out each day in the resource usage view by greying out the day. Exceptions for "A.N Other" leave the day as white (but as expected dont allow any work to be scheduled for those days). Is it possible to make the resource usage view highlight resource execptions in the same way plan exceptions are?

This would make it clearer in identfying when a resource is not available as apposed to when a resource is under allocated.

Thanks,
Graham.
Reply With Quote
  #2  
Old 02-05-2009
JulieS
 
Posts: n/a
Re: Highlighting Holidays in the resource view

Hello Graham,

You can change the non-working time display in the Resource Usage
view to show a selected resource's exceptions. Choose Format >
Timescale and select the Non-working time tab. Click the drop down
under "Calendar" and select the resource's name. That applies the
selected resource's exceptions to the background of the entire
timescaled portion of the view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"maharg" <maharg.3rex3c@DoNotSpam.com> wrote in message
news:maharg.3rex3c@DoNotSpam.com...
>
> Hi,
>
> I'm using MS project 2007. We have a central resource plan of
> which all
> project plans use. Within this we keep individuals holidays up to
> date
> (tools>change working time>"person a">add an exception).
>
> Is there a way to make these holidays clearer in the resouce usage
> view?
>
> Exceptions from the standard (project calendar) (national
> holidays,
> weekends etc) block out each day in the resource usage view by
> greying
> out the day. Exceptions for "A.N Other" leave the day as white
> (but as
> expected dont allow any work to be scheduled for those days). Is
> it
> possible to make the resource usage view highlight resource
> execptions
> in the same way plan exceptions are?
>
> This would make it clearer in identfying when a resource is not
> available as apposed to when a resource is under allocated.
>
> Thanks,
> Graham.
>
>
> --
> maharg
> ------------------------------------------------------------------------
> maharg's Profile: http://forums.techarena.in/members/94971.htm
> View this thread:
> Highlighting Holidays in the resource view
>
> http://forums.techarena.in
>



Reply With Quote
  #3  
Old 05-05-2009
Member
 
Join Date: Apr 2009
Posts: 4
Re: Highlighting Holidays in the resource view

Hi, thanks for the response.

That is kind of what I am looking for but not quite. It would be nice to apply the background colour just to the resource that is effected by that particular exception rather than the entire view. However I would assume now that this is not possible.

Thanks,
Reply With Quote
  #4  
Old 05-05-2009
JulieS
 
Posts: n/a
Re: Highlighting Holidays in the resource view

You're welcome for the information and thanks for the feedback. You
are correct, the background color applies to the entire view -- not
just to the assignments for the specific resource.

Julie
"maharg" <maharg.3rphnf@DoNotSpam.com> wrote in message
news:maharg.3rphnf@DoNotSpam.com...
>
> Hi, thanks for the response.
>
> That is kind of what I am looking for but not quite. It would be
> nice
> to apply the background colour just to the resource that is
> effected by
> that particular exception rather than the entire view. However I
> would
> assume now that this is not possible.
>
> Thanks,
>
>
> --
> maharg
> ------------------------------------------------------------------------
> maharg's Profile: http://forums.techarena.in/members/94971.htm
> View this thread:
> Highlighting Holidays in the resource view
>
> http://forums.techarena.in
>



Reply With Quote
Reply

  TechArena Community > Technical Support > Computer Help > Office Help > Microsoft Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "Highlighting Holidays in the resource view"
Thread Thread Starter Forum Replies Last Post
Transferring field info from 'Gantt Chart' view to 'Resource Usage' view MikeCrayon Microsoft Project 6 24-09-2011 02:32 AM
MS Project Cost per resource in Gantt View Projectproject Windows Software 1 20-04-2011 07:27 PM
Summarize Task on Resource Usage View/Reports Ann Microsoft Project 3 08-01-2011 06:07 AM
Resource usage view CBnation Microsoft Project 4 07-10-2010 05:24 PM
Resource Usage View - adding columns only available in Task Views Pam Microsoft Project 6 09-09-2009 10:40 PM