| Highlighting Holidays in the resource view
Hi, I'm using MS project 2007. We have a central resource plan of which all project plans use. Within this we keep individuals holidays up to date (tools>change working time>"person a">add an exception). Is there a way to make these holidays clearer in the resouce usage view? Exceptions from the standard (project calendar) (national holidays, weekends etc) block out each day in the resource usage view by greying out the day. Exceptions for "A.N Other" leave the day as white (but as expected dont allow any work to be scheduled for those days). Is it possible to make the resource usage view highlight resource execptions in the same way plan exceptions are? This would make it clearer in identfying when a resource is not available as apposed to when a resource is under allocated. Thanks, Graham. |
|
#2
| |||
| |||
| Re: Highlighting Holidays in the resource view
Hello Graham, You can change the non-working time display in the Resource Usage view to show a selected resource's exceptions. Choose Format > Timescale and select the Non-working time tab. Click the drop down under "Calendar" and select the resource's name. That applies the selected resource's exceptions to the background of the entire timescaled portion of the view. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "maharg" <maharg.3rex3c@DoNotSpam.com> wrote in message news:maharg.3rex3c@DoNotSpam.com... > > Hi, > > I'm using MS project 2007. We have a central resource plan of > which all > project plans use. Within this we keep individuals holidays up to > date > (tools>change working time>"person a">add an exception). > > Is there a way to make these holidays clearer in the resouce usage > view? > > Exceptions from the standard (project calendar) (national > holidays, > weekends etc) block out each day in the resource usage view by > greying > out the day. Exceptions for "A.N Other" leave the day as white > (but as > expected dont allow any work to be scheduled for those days). Is > it > possible to make the resource usage view highlight resource > execptions > in the same way plan exceptions are? > > This would make it clearer in identfying when a resource is not > available as apposed to when a resource is under allocated. > > Thanks, > Graham. > > > -- > maharg > ------------------------------------------------------------------------ > maharg's Profile: http://forums.techarena.in/members/94971.htm > View this thread: > Highlighting Holidays in the resource view > > http://forums.techarena.in > |
|
#3
| |||
| |||
| Re: Highlighting Holidays in the resource view
Hi, thanks for the response. That is kind of what I am looking for but not quite. It would be nice to apply the background colour just to the resource that is effected by that particular exception rather than the entire view. However I would assume now that this is not possible. Thanks, |
|
#4
| |||
| |||
| Re: Highlighting Holidays in the resource view
You're welcome for the information and thanks for the feedback. You are correct, the background color applies to the entire view -- not just to the assignments for the specific resource. Julie "maharg" <maharg.3rphnf@DoNotSpam.com> wrote in message news:maharg.3rphnf@DoNotSpam.com... > > Hi, thanks for the response. > > That is kind of what I am looking for but not quite. It would be > nice > to apply the background colour just to the resource that is > effected by > that particular exception rather than the entire view. However I > would > assume now that this is not possible. > > Thanks, > > > -- > maharg > ------------------------------------------------------------------------ > maharg's Profile: http://forums.techarena.in/members/94971.htm > View this thread: > Highlighting Holidays in the resource view > > http://forums.techarena.in > |
![]() |
|
| Thread Tools | Search this Thread |
| |
Similar Threads for: "Highlighting Holidays in the resource view" | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Transferring field info from 'Gantt Chart' view to 'Resource Usage' view | MikeCrayon | Microsoft Project | 6 | 24-09-2011 02:32 AM |
| MS Project Cost per resource in Gantt View | Projectproject | Windows Software | 1 | 20-04-2011 07:27 PM |
| Summarize Task on Resource Usage View/Reports | Ann | Microsoft Project | 3 | 08-01-2011 06:07 AM |
| Resource usage view | CBnation | Microsoft Project | 4 | 07-10-2010 05:24 PM |
| Resource Usage View - adding columns only available in Task Views | Pam | Microsoft Project | 6 | 09-09-2009 10:40 PM |