Hello,
I have a project which has some historical data on it, and then estimates going forward over 5 years.
I would like to print out the gannt chart between two date (say 1 Jan 09, to 30 Jun 2010). I would like to see any task which may start in 2008 and extends into 2009, but I only want to see that part of the bar which falls in 2009. Similarly, for tasks which start in 2010, and extend past 30 Jun 2010. And obviously I also want to see all the tasks which start and end between those dates.
I've looked at the thread titles here, and read the FAQ's, but I can't see anything which indicates how to do this.
Thanks.