Thread: Work vs. Duration

  1. #1
    Join Date
    Sep 2005
    Posts
    227

    Work vs. Duration

    I want to have a task with a duration of X days, and have multiple resources assigned to the task for varying hours. The total work should not be equal to the duration. If I am trying to reduce the work on any resource in the Resource Usage sheet, MSP reduces the dueartion of the task. Can anyone tell me a way to adjust work without affecting duration. Thanks.

  2. #2
    Join Date
    Feb 2006
    Posts
    335

    Re: Work vs. Duration

    You can try to temporarily set the task as fixed duration and uncheck effort driven. You should try to create the task with X duration and then when you assign work for each resource then Project will calculate the assignment units necessary to balance the work over the duration.

  3. #3
    Join Date
    Nov 2005
    Posts
    609
    You can also manually distribute the work (non-linearly) by using the Task Usage view (View/Task Usage...). You will need to make the task Fixed duration non-effort driven just as stated above. Are you using task calendars which have odd working times? Even with fixed duration tasks, non-working time can adjust the schedule (usually finish date). Please give us an example of what you are trying to do and include details like the definition of working time in your task calendar.

  4. #4
    Join Date
    Sep 2005
    Posts
    227

    Re: Work vs. Duration

    We just took a 5 day calendar and added some company holidays as non-working time. Both the tasks and resources are assigned to the company calendar. We have then taken a task, set a duration and assign a resource. But the fixed duration and effort driven off, schedule ignores resource calendars. If we adjust the resource hours in the resource usage view the duration changes. When we reset the duration, the resource loading resets. The tasks are paint drying type tasks, Activities that go on whether or not any hours are being charged.

  5. #5
    Join Date
    Sep 2005
    Posts
    1,370

    Re: Work vs. Duration

    I don't understand why you need to assign this task to any calendar. Usually tasks are assigned no calendar, and the effect of any holidays MS Project automatically takes from the "Standard (Project Calendar)". You will need to assign a task a calendar of its own, and switch off the dependence on resource calendars, if for some reason it needs to run to a different calendar to all other tasks (e.g. weekend work). So try to set up your holidays in the Standard (Project Calendar) and then try selecting no calendar for this task. After that make it fixed duration and then switch of effort driven.

  6. #6
    Join Date
    Sep 2005
    Posts
    227

    Re: Work vs. Duration

    Thats absolutely correct. We are trying to make this work, everything is and has been from the first - fixed duration, effort driven off. My thoughts are that something in the resource was at play and the only way I could see to confirm or verify that is to ignore the resource schedule. The only way to do that is to set a calendar for the task, even if it is the default calendar.

  7. #7
    Join Date
    Oct 2005
    Posts
    1,217

    Re: Work vs. Duration

    If you would like, then you can try to zip the file and send it to me. I wont gurantee you, but I will take a look and see that I can find the issue. Also, try to give me some details in the message about what specific tasks are causing this issue.

Similar Threads

  1. Desired Behavior when changing work or duration
    By Lokius in forum Microsoft Project
    Replies: 7
    Last Post: 03-05-2012, 06:11 PM
  2. Difference between fixed work, duration and units
    By Amitgujaran in forum Microsoft Project
    Replies: 5
    Last Post: 17-12-2011, 09:37 PM
  3. Microsoft Project - Duration, Work, Units?
    By emloy4it in forum Microsoft Project
    Replies: 4
    Last Post: 18-12-2010, 10:44 AM
  4. Duration vs. Actual Work
    By hatred in forum Microsoft Project
    Replies: 3
    Last Post: 22-04-2010, 05:13 AM
  5. Setting up work effort that is different from Duration
    By Rachel G in forum Microsoft Project
    Replies: 2
    Last Post: 31-01-2008, 03:30 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,710,847,785.83157 seconds with 16 queries