I want to have a task with a duration of X days, and have multiple resources assigned to the task for varying hours. The total work should not be equal to the duration. If I am trying to reduce the work on any resource in the Resource Usage sheet, MSP reduces the dueartion of the task. Can anyone tell me a way to adjust work without affecting duration. Thanks.