We are working with Microsoft Project 2007. We’ve created two Projects including 5 tasks each with different durations for projects. For reference, let me named these projects as A and B. All these tasks have Finish to Start link which should be started right after its predecessor. Also Task Tasks A3 and B4 must finish at the same time. After some research I thought it could be done by using Finish to Finish link.
Well I did the same and it works as well but not as I assumed. It stops the neat stacking of tasks B1,B2,B3 and B4, they become disjointed with large gaps between some of their ends and the start of the next task. Any idea what am I making wrong? Somebody please help me to get it done. Many thanks.